Permit: T10BU00752

Parcel: 104061830

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
11/09/2012 GRADING - INTERMEDIATE Approved
08/07/2012 GRADING - INTERMEDIATE Continued I MET THE OWNER ON THIS SITE AND HAVE DISCUSSED WHAT IT IS THAT HE IS PLANNING ON DOING TO COMPLETE THIS SITE AND CLOS OUT ALL OF THE OPEN PERMITS. THEY WILL BE CONTINUEING WITH THE WORK ON THIS SITE IN THE NEXT 2 WEEKS BUT NO SET SCHEDULE AT THIS TIME. THEY WILL ADVISE ME WHEN THEY START THE WORK SO THAT I CAN MEET WITH THEM AND SEE WHAT THE SCHEDULE IS AT THAT TIME.
07/18/2012 GRADING - INTERMEDIATE Continued NO ONE THIS SITE AT THIS TIME, WILL CONTINUE TO CHECK ON THIS SITE EVERY 2 WEEKS TILL I FIND SOMEONE PERFORMING WORK.
06/28/2012 GRADING - INTERMEDIATE Continued SUBCONTRACTORS WORKING ON BLDG, NO SITE WORK BEING COMPLETED.
NO STORM WATER CONCERNS AT THIS TIME.
06/22/2012 GRADING - INTERMEDIATE Continued NO ACTIVITY ON SITE, SITE WORK HAS NOT BEEN COMPLETED.
04/02/2012 GRADING - INTERMEDIATE Continued MET WITH SUPERINTENDENT/OWNER ON SITE DISCUSSED COMPLETING PROJECT. SITE WORK MUST MATCH THE APPROVED GRADING PLAN OR AN APPROVED GRADING PLAN
MUST BE MADE AVAILABLE THAT SHOWS WHAT WAS CONSTRUCTED.

NO STORM WATER CONCERNS AT THIS TIME
03/20/2012 GRADING - INTERMEDIATE Continued NO CONTACT ON SITE - RAIN DAY, SITE MOSTLY COMPLETED.
NO STORM WATER CONCERNS
02/14/2012 GRADING - INTERMEDIATE Continued NO CHANGES, CONTRACTOR HAS NOT CALLED IN AN INSPECTION TO FINAL SITE.
06/14/2011 GRADING - INTERMEDIATE Continued PEDESTRIAN ACCESS SIDEWALK FROM ROW DOES NOT MEET SLOPE REQUIREMENTS.
SIDEWALK HAS A 7.4% SLOPE WITH A RISE > 6"/NEED HAND RAILING FOR RAMP PER ANSI.
SIDEWALK CROSS SLOPE IS >2%/DOES NOT MEET COT DEV STD AND ANSI.
06/14/2011 GRADING - INTERMEDIATE Continued MARK EUGLOSKY 444-2883
04/20/2011 GRADING - INTERMEDIATE Continued 1) OK FOR CHANGE TO SIDEWALK DISSCUSSED W/ PROPERTY OWNER.
2) OPENING SHOWN IN CONCRETE CURBING @ ISLAND NEXT TO HC PARKING SPACE.
3) ENSURE SLOPE ON PEDESTRIAN ACCESS SIDEWALK OFF OF JIM HOWAED PLACE IS NOT GREAYER THAN 5% - MEASURED 5.3% ON FORMS.

NO STORM WATER CONCERNS

CALL FOR RE-INSPECTION
04/19/2011 GRADING - INTERMEDIATE Continued CONTRACTOR WORKING ON CURBING, CURB OPENINGS, ISLANDS AND DRIVEWAYS. NO STORM WATER CONCERNS AT THIS TIME
04/04/2011 GRADING - INTERMEDIATE Continued DISCUSSED SITE WORK AND ELEVATIONS FOR PAVING. DISCUSSED STORM WATER ISSUES W/ DRAINAGE CHANNEL ADJACENT TO SOUTH PERIMETER.
03/23/2011 GRADING - INTERMEDIATE Continued 1) ADD TEMP SEDIMENT CONTROLS ALONG PERIMETER IN THE SOUTHEAST CORNER IN ORDER TO PREVENT DISTURBED SOIL FROM ENTERING THE PUBLIC DRAINAGE WAY.
2) PRIOR TO FINAL APPROVAL ENSURE AN ELEVATION CERT. FOR THE BLDG PAD IS SUBMITTED AND APPROVED BY THE COT.
3) PRIOR TO FINAL APPROVAL ENSURE A BASIN/DRAINAGE CERT STATEMENT FROM THE ENG/ARCH OF RECORD IS SUBMITTED AND APPROVED BY THE COT.
4) CALL FOR INSPECTION PRIOR TO PAVING.
5) CALL FOR INSPECTION FOR ANY SIGNIFICANT CHANGES TO THE APPROVED PLAN.