Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T10BU00503
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/15/2012 | GRADING - INTERMEDIATE | Approved | ||
01/31/2012 | GRADING - INTERMEDIATE | Continued | GRADING ON EAST SIDE SITE AND LANDSCAPING ON WEST SIDE. | |
01/20/2012 | GRADING - INTERMEDIATE | Continued | NO CONCERNS AT THIS TIME. | |
01/12/2012 | GRADING - INTERMEDIATE | Continued | NO CONCERNS AT THIS TIME. | |
12/30/2011 | GRADING - INTERMEDIATE | Continued | LOOKED OVER THE SITE WORK THAT IS HAPPENING AT THIS TIME. THE CONTRACTOR IS WORKING ON CONSTRUCTION OF THE ELEPHANT ENCLOSURE AND PLACEMENT OF ROCK RIP RAP IN VARIOUS LOCATIONS ADJACENT TO THE WASH IN THE SOUTHWEST QUADRANT. | |
12/23/2011 | GRADING - INTERMEDIATE | Continued | GOT WITH ASHTON ABOUT TRACK OUT .THAT NEEDS CLEANING . | |
12/08/2011 | GRADING - INTERMEDIATE | Continued | NO GRADING WORK BEING DONE TODAY. | |
11/07/2011 | GRADING - INTERMEDIATE | Continued | TRACK OUT ON STREETS . | |
11/03/2011 | GRADING - INTERMEDIATE | Continued | WORKING ON SIDE WALKS. | |
10/31/2011 | GRADING - INTERMEDIATE | Continued | ADDING HEADER CURB AT CITATION WASH FOOTER 12''&12'' PER RED LINES TO BE AP BY CITY OF TUCSON . | |
10/28/2011 | GRADING - INTERMEDIATE | Continued | WORKING ON SIDE WAIK ON WEST SIDE OF JOB SITE. | |
10/27/2011 | GRADING - INTERMEDIATE | Continued | SIDE WALK BEING FORMED DOWN BY INCLOSURE. | |
10/19/2011 | GRADING - INTERMEDIATE | Continued | LETTER FROM ROBERT JUST FOR EAST PARKING LOT ON FILE. | |
10/14/2011 | GRADING - INTERMEDIATE | Continued | PARKING LOT ON SOUTHEAST SIDE OK.WEST SIDE INTERMEDIATE GRADING I LOOKED AT PROVIED ENGINEERS CERTS. | |
09/20/2011 | GRADING - INTERMEDIATE | Partial Approval | Began paving of east parking lot today, subgrade approved. | |
09/09/2011 | GRADING - INTERMEDIATE | Continued | Contractor ready to pave parking lot on east edge of project and working on entrance on south edge of project. | |
08/25/2011 | GRADING - INTERMEDIATE | Partial Approval | Subgrade approved, contractor begining to place Ab on east parking lot. | |
08/24/2011 | GRADING - INTERMEDIATE | Partial Approval | Grading for subgrade on west parking lot, remove all organic debris from fill and compact loose material prior to placing AB. | |
08/17/2011 | GRADING - INTERMEDIATE | Partial Approval | Vertical conc. curb in east parking lot OK | |
07/07/2011 | GRADING - INTERMEDIATE | Partial Approval | Contractor placed grouted rip rap at lift station outfall, approved. | |
06/29/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to place rip rap at storm outfall from lift station. | |
06/10/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to backfill DI pipe from vault to outlet. | |
06/06/2011 | GRADING - INTERMEDIATE | Partial Approval | Contractor backfilled 8" HDPE strom pipe to lift station, shaded 10" DI pipe from lift station. | |
06/03/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to backfill 8" HDPE pipe from pump station and 10" DI discharge pipe from pump station. | |
05/16/2011 | GRADING - INTERMEDIATE | Partial Approval | LOOKED AT THE JUNCTION STRUCTURE IN THE NORTHWEST CORNER OF THE SITE. CREW SET THE TOP OF THE STRUCTURE IN PLACE AND WILL BE WORKING ON THE BACKFILL OF THE AREA. tHIS PARTIAL APPROVAL IS FOR THE BACKFILL OF THE STRUCTURE ONLY. | |
04/22/2011 | GRADING - INTERMEDIATE | Partial Approval | OK to backfill 8" Hdp pipe from Elephant barn to outfall. | |
04/19/2011 | GRADING - INTERMEDIATE | Partial Approval | Approved 8" Hdp pipe for backfill, 2 runs from Barn area toward pool. | |
03/23/2011 | GRADING - INTERMEDIATE | Continued | Grading and utility work continuing, pool and premeter walls under construction at this time | |
02/09/2011 | GRADING - INTERMEDIATE | Continued | Site work continuing | |
01/19/2011 | GRADING - INTERMEDIATE | Continued | Contractor excavating for Elephant pool, also stockpiled 8000cy of unsuitable material found onsite. I asked that they install storm controls along northwest premeter. |