Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
01/14/2013 GRADING - INTERMEDIATE Continued SITE MOSTLY COMPLETE, NO SIGNIFICANT CHANGES TO THE APPROVED PLANS.
01/04/2013 GRADING - INTERMEDIATE Continued NO CHANGES AND/OR CONCERNS AT THIS TIME
12/11/2012 GRADING - INTERMEDIATE Continued BLDG NEARING COMPLETION, HOWEVER MOST SITE WORK STILL NEEDED.
NO STORM WATER CONCERNS AT THIS TIME
08/20/2012 GRADING - INTERMEDIATE Continued CHECKED THE SITE TOO SEE WHAT WORK HAS BEEN ACCOMPLISHED SINCE MY LAST SITE VISIT. CREWS CONTINUE TO WORK ON THE BUILDING CONSTRUCTION AND HAVE STARTED WORK OUTSIDE THE BUILDING ON THE NORTHSIDE OF THE SITE. CREWS ARE WORKING ON THE GRADING FOR THE TRASH ENCLOSURE AND FORMING OF SOME OF THE SIDEWALK
07/19/2012 GRADING - INTERMEDIATE Continued CREWS CONTINUE TO WORK ON THE BUILDING AT THIS TIME. ASK THE CREW TO MAKE SURE THAT THEY CONTINUE TO PICK UP THE SITE, AND MAKE SOME MINOR ADJUSTMENTS IN THE SWPPP CONTROLS.
07/03/2012 GRADING - INTERMEDIATE Continued NO SITE WORK AT THIS TIME
06/28/2012 GRADING - INTERMEDIATE Continued CONTRACTOR WORKING ON BLDG ONLY, NO SITE WORK AT THIS TIME.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/22/2012 GRADING - INTERMEDIATE Continued NO CONCERS AND OR PROBLEMS AT THIS TIME. CONTRACTOR WORKING ON BLDG ONLY, NO SITE WORK AT THIS TIME
06/21/2012 GRADING - INTERMEDIATE Continued NO SITE WORK BEING DONE AT THIS TIME.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/07/2012 GRADING - INTERMEDIATE Continued 1) STOCKPILED SOIL HAS BEEN MOVED AWAY FROM THE PERIMETER OF THE SITE.
2) CONTINUE TO SWEEP UP ANY TRACKED SOIL OFF OF ADJACENT ROADWAY.
3) CALL FOR INSPECTION FOR ANY CHANGES TO THE ORIGINAL GRADING PLAN AND/OR ANY CONCERNS WITH SITE WORK.
05/16/2012 GRADING - INTERMEDIATE Correction Required CORRECTION REQUIRED:
REMOVE STOCKPILED SOIL FROM SE CORNER OF SITE AND OR BRING SOIL BACK ONTO SITE AND PLACE SEDIMENT CONTROLS AROUND IT.

CORRECT BY 7 WORKING DAYS
NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION.
05/14/2012 GRADING - INTERMEDIATE Continued NO CHANGES AND/OR STORM WATER CONCERNS AT THIS TIME
05/01/2012 GRADING - INTERMEDIATE Continued NO SIGNIFICANT CONCERNS AT THIS TIME
04/18/2012 GRADING - INTERMEDIATE Continued CONTRACTOR CALLED IN FOR AN INSPECTION ON THE RE-BAR LAY OUT FOR THE FOOTING OF THE FOUNDATION. HAD CONTRACTOR CALL BLDG INSPECTOR.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
04/04/2012 GRADING - INTERMEDIATE Continued 1) SWEEP UP TRACKING OFF OF PUBLIC ROADWAY AND RIGHT - OF WAY.
2) ADD SEDIMENT CONTROLS ALONG WEST SIDE NEAR EXISTING CATCH BASIN.