Permit: T09BU01243

Parcel: 11204370H

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
03/24/2011 GRADING - INTERMEDIATE Approved
01/14/2011 GRADING - INTERMEDIATE Approved
01/12/2011 GRADING - INTERMEDIATE Continued NO CHANGES, NO ACTIVITY ON SITE
WORK MOSTLY COMPLETED
12/10/2010 GRADING - INTERMEDIATE Continued MAJORITY OF SITE WORK COMPLETED, WAITING FOR LANDSCAPING, AND RAILING FOR PEDESTRIAN ACCESS RAMPS. PARKING, ACCESS, DRAINAGE AND TRASH ENCLOSURE HAS BEEN COMPLETED PER THE APPROVED PLAN.
10/22/2010 GRADING - INTERMEDIATE Continued MET W/ SUPERINTENDENT TO DISCUSS ADAAG ACESS OFF OF FT LOWELL. ACCESS RAMP IS SHOWN ON PLANS HOWEVER ELEVATIONS AND SLOPES WILL BE DIFFERENT THAN PLANS.
ENSURE ACCESS RAMP RUN SLOPES ARE NO >8.3% AND CROSS SLOPE IS NO > 2%. HANDRAILING IS REQUIRED ON BOTH SIDES OF RAMP.

NO STORM WATER CONCERNS AT THIS TIME
10/08/2010 GRADING - INTERMEDIATE Continued SITE WORK ALONG WASH HAS BEEN COMPLETED. BANK PROTECTION AND WALL HAS BEEN INSTALLED. >.5" RAIN NO SIGNIFICANT DAMAGE TO SLOPE OR ROCK RIP RAP. NO STORM WATER CONCERNS AT THIS TIME
09/01/2010 GRADING - INTERMEDIATE Continued 1) FOOTER FOR DRAINAGE OUTLET AT REAR (SOUTH SIDE) OF BLDG AND PARKING AREA HAS BEEN POURED. ROCK RIP RAP TO BE INSTALLED AT A LATER TIME.
2) ENSURE CONSTRUCTION DEBRIS AND SPOILS FROM TRENCH IS REMOVED FROM EXISTING DRAINAGE WAY.
3) SWEEP UP TRACKED SOIL OFF OF PUBLIC ROADWAYS ON A ROUTINE BASIS.
4) CALL FOR INSPECTION FOR FOLLOW UP AND/OR ANY CONCERNS/QUESTIONS.