Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/29/2010 | GRADING - INTERMEDIATE | Approved | ||
| 05/06/2010 | GRADING - INTERMEDIATE | Continued | CHECKED HC PARKING AREA AT SE CORNER OF PARK | |
| 05/03/2010 | GRADING - INTERMEDIATE | Continued | WALKED SITE W/ CONTRACTOR: CHANGES MADE TO CONCESSION BLDG, MINIMAL CHANGES MADE TO SITE WORK. SURFACE OF HC PARKING AREA IS CHIP SEAL OVER ASPHALT, SURFACE MUST BE STABLE AND FIRM TO BE ADAAG COMPLIANT. NO STORM WATER CONCERNS AT THIS TIME |
|
| 03/05/2010 | GRADING - INTERMEDIATE | Continued | NO CHANGES TO APPROVED PLANS | |
| 01/20/2010 | GRADING - INTERMEDIATE | Continued | NO STORM WATER CONCERNS AT THIS TIME, CONTRACTOR MUST CONTINUE TO SWEEP UP TRACKED MATERIALS OFF PUBLIC ROADWAY ROUTINELY. NO GRADING CONCERNS OR CHANGES |
|
| 01/11/2010 | GRADING - INTERMEDIATE | Continued | NO CHANGES OR CONCERNS AT THIS TIME. CONTRACTOR MUST ENSURE THAT REQUIRED STORM WATER MAINT. INSPECTIONS ARE PERFORMED AND DOCUMENTED PER PLAN. CONTRACTOR MUST CONTINUE TO SWEEP UP ANY TRACKED MATERIAL OFF OF PUBLIC ROADWAYS ROUTINELY. |
|
| 12/31/2009 | GRADING - INTERMEDIATE | Continued | CONTRACTOR WORKING ON SUBGRADE OF BALL FIELD. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |