Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2009 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) OK FOR CONCRETE S.T.O.I. |
|
| 07/22/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) 2ND LEVEL BELOW FLOOR 2) DWV WITH TEST OK 3) RECALL FOR PRE-SLAB INSPECTION |
|
| 07/21/2009 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 07/20/2009 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) BACK PITCHED SECTIONS NOT APPROVED |
|
| 07/15/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) FIRST FLOOR ROUGH INSTALLED-OK 2) OK TO COVER |
|
| 07/14/2009 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | CANCELLED PER MIKE |