Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/05/2010 | PLUMBING - FINAL | Approved | IVRS - Inspection :* 1) LABEL ELECTRICAL PANELS 2) CHECK AND ADJUST PRV'S AS NEEDED ON ALL BLDGS 3) HANDLES BURIED 4) PROPER CLEANOUT PLUGS/COVERS AT KS'S |
|
| 03/30/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) BREAD TIES ARE FOR BREAD BAGS-PROVIDE APPROVED PLASTIC PIPE SUPPORTS FOR DW DRAIN HOSES 2) DW HAMMER ARRESTORS PER PLAN 3) SEAL SINKS TO COUNTER |
|
| 03/26/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) EXTERIOR CLEANOUTS NOT TERMINATED 2) HB VACUUM BREAKERS, ALSO PLANS SPEC LOOSE KEY 3) DW NOT INSTALLED, PLAN SPECIFIES HAMMER ARRESTORS 4) SUPPORT FOR EXPANSION TANKS 5) DID NOT WALK BLDG BECAUSE WORK IS NOT COMPLETE |