Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2009 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 01/09/2009 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 11/18/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST TO POINT OF EXISTING 1. MAKE REPAIR WITH RUN TEST AT POINT OF CONNECTION WITH INSPECTION FOR FALL 2. PROVIDE STAMPED SEALED LETTER FROM TIM PLEGER ENGINEER FOR 2" FLOOR DRAINS REINSPECTION PIPING OK PIPE WRAPS & PRIMERS & FLOOR DRAINS OK NEED NOTE #2 ONLY |
|
| 11/12/2008 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* SLOPE. PROVIDE 1/4" ALSO, DITCH WET 3" FDS SPECIFIED |