Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* LOADING AREA RAMP -- OK TO POUR |
|
| 01/14/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PRE-GROUT OK |
|
| 01/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SITE WALL @ 0'-4' -- APPROX. 140' SOUTH & SW - W PORTIONS OF SITE -- OK TO GROUT |
|
| 12/31/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SITE WALL |
|
| 12/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) MISSING CONTROL JOINTS REBAR |
|
| 11/10/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SLAB FOR MAIN BUILDING REMOVED -- RESET REBAR AS PER RFI #SK3 10/30/08 -- OK TO POUR SOUTH HALF TO BE POURED FIRST -- SPECIAL INSPECTED |
|
| 10/14/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) RESTROOM AREAS AT E/7.25-8, F/5/7.25-8 2) OK TO POUR FOOTINGS 3) RESTROOM SLAB TO CONTROL JOINTS E/7.25-8, F5/7.25-8 OK TO POUR |
|
| 10/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TOE DOWN FOOTING LINE G/1-8; COLUMN FOOTING @ LINE F.5/7.5 -- OK TO POUR PROGRESS AREAS |
|
| 10/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
| 10/01/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONTINUOUS PERIMETER FOOTINGS LINES A/1 TO G/1, A/1 TO A/8, A/8 TO G/8 (F3-3, F6-6) OK TO POUR |
|
| 09/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONCRETE GRADE BEAMS @ LINES 2,6,7 AS PER GB SCHEDULE PAGE S200 -- OK TO POUR |
|
| 09/17/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONCRETE GRADE BEAMS @ LINES 3, 4, 5 -- AS PER GB SCHEDULE, PAGE S200 -- OK TO POUR PROGRESS AREAS |
|
| 09/12/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 6 @ COLUMN FOOTINGS (F-3's) @ SOUTH SIDE - OK TO POUR AS PER FOOTING SCHEDULE |
|
| 09/11/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NORTH SIDE COLUMN FOOTINGS - LINE 1/A, C, D, E, F, G (8 @ F3's) EAST SIDE LINE A/2-7 (F6 @ 6) OK TO POUR PROGRESS AREAS DETAIL #402 |
|
| 09/10/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 2 @ COLUMN FOOTINGS (F6) - LINE G/6-7 OK TO POUR |
|
| 09/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 4 @ F6 - LINE G/2-5 AS PER DETAIL #405, PAGE S400 COLUMN FOOTINGS - OK TO POUR |