Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T08BU02059

Parcel: 141100080


Addresses:

7501 S KOLB RD

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
06/21/2011 GRADING - INTERMEDIATE Approved
06/14/2011 GRADING - INTERMEDIATE Continued CREWS HAVE COMPLETED MOST OF THE PATHWAY WORK AND MOST OF THE LANDSCAPING, THIS SITE WILL BE INSPECTED DURING THIS WEEK TO SEE WHAT HAS BEEN FULLY COMPLETED.
05/11/2011 GRADING - INTERMEDIATE Continued CREWS CONTINUE TO WORK ON THE GRADING OF THE PATHWAYS, AND THE PLACEMENT OF THE DECOMPOSED GRANITE AS NEEDED THROUGHOUT THE SITE. ALSO PLACEMENT OF THE ABC FOR THE ASPHALT PATH THAT WILL BE POURED IN THE NEXT 2 WEEKS IF POSSIBLE.
04/13/2011 GRADING - INTERMEDIATE Continued DROVE THROUGH THE SITE TO SEE WHAT THE CONTRACTOR HAS ACCOMPLISHED SINCE MY LAST VISIT. THEY ARE CURRENTLY WORKING ON THE PLACEMENT OF THE DG FOR ONE OF THE PEDESTRIAN PATHS FROM THE PEDESTRIAN BRIDGE EAST TO RITA ROAD. CREWS ARE ALSO WORKING ON THE MINOR GRADING IN THE AREA WHERE THE OLD RAILROAD SERVICE TRACKS WERE LOCATED, ALSO WORKING IN THE AREAS OF THE CONVENIENCE LOCATIONS THROUGHOUT THE SITE. MET WITH THE CONTRACTOR WHO ADVISES THAT THEY WILL TRY TO PLACE PAVEMENT FOT THE PATHWAY WITHIN THE NEXT 2 WEEKS
03/09/2011 GRADING - INTERMEDIATE Continued MET ON-SITE WITH THE CONTRACTOR AND DISCUSSED WHAT IS HAPPENING. CURRENTLY HUNTER IS GRADING THE ENTRANCE INTO THE SITE OFF OF KOLB ROAD AND ARE FORMING AND POURING THE CURBS FOR THIS SAME AREA. IN THE PAST FEW WEEKS THEY HAVE GRADED THE AREAS FOR THE BRIDGE ABUTTMENTS AND HAVE POURED THEM, ALONG WITH TWO OF THE CONCRETE ISLANDS EAST OF THE PEDESTRIAN BRIDGE. NEXT WEEK THEY WILL BE WORKING ON THE MINOR GRADING OF THE PATHS IN THE AREAS WHERE THERE IS NO ADDITIONAL WORK TO BE PERFORMED.
AAA LANDSCAPING IS WORKING ON INSTALLATION OF THE IRRIGATION LINES. SOME OF THE MAINLINES HAVE BEEN PREVIOUSLY PLACED, CURRENTLY THEY ARE INSTALLING SOME OF THE FEEDER LINES.
02/14/2011 GRADING - INTERMEDIATE Continued CREWS WORKING ON THE FOLLOWING ITEMS: CREW WORKING EAST OF KOLB ON THE ENTRANCE INTO THE SITE AND THE SEWER SERVICE. CREW WORKING IN THE COMFORT STATION AREA. AAA WORKING ON INSTALLING THE IRRIGATION LINE AT THE WEST END. TRUCK HAUL DUMPING MATERIAL IN THE AREA OF THE PEDESTRIAN BRIDGE ABUTMENTS.
02/07/2011 GRADING - INTERMEDIATE Continued CREWS WORKING ON THE FOLLOWING ITEMS TODAY: INSTALLING PIPE RUNS FROM KOLB TOWARDS THE COMFORT STATION. POURING COLUMNS AT THE COMFORT STATION. GRADING EAST OF THE DRAINAGE DITCH NORTH OF THE PEDESTRIAN BRIDGE TO AN AREA WEST OF THE RAILROAD CROSSING. AAA STILL WORKING ON THE GRUBBING AND PREPARING FOR THE UTILITY WORK.
02/03/2011 GRADING - INTERMEDIATE Continued WATCHED THE CREW INSTALL THE REMAINING RCP'S AT THE ENTRYWAY AND STACK AND RAISE A MANHOLE AT THE SAME LOCATION. THIS AREA HAS ONE MORE MANHOLE TO BE RAISED BUT THIS WORK WILL NOT BE DONE TILL NEXT WEEK. THERE WILL BE A GROUND BREAKING CEREMONY ON FRIDAY FOR THIS SITE, THE WORK IN THIS AREA WILL BE CANCELLED DURING THAT TIME, AND WILL RESUME LATER IN THE DAY.
02/02/2011 GRADING - INTERMEDIATE Continued THE CONTRACTOR IS WORKING ON THE INSTALLATION OF THE CONCRETE PIPES EAST OF KOLB, COMFORT STATION, AND CONTINUES WITH THE REMOVAL OF PLANTS AND INSTALLATION OF VISUAL INDICATORS IN THE HIGHLY VEGITATIVE AREAS AND THE REMOVAL OF PLANTS.