Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date |
Description |
Inspector |
Results |
Comments |
| 01/31/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Approved |
MET OUT ONSITE WITH THE CONTRACTOR, THEY ARE CURRENTLY WORKING ON THE COMFORT STATION FOOTER LAYOUT AND ON THE PIPE INSTALLATIONS EAST OF KOLB ROAD. ALSO A CREW FROM AAA LANDSCAPING IS WORKING ON THE REMOVAL OF VEGETATION ON THE EAST HALF OF THE SITE, THIS WORK SHALL CONTINUE THROUGH THE WEEK. THEY ARE INSTALLING THE STORMWATER CONTROLS AS THEY CLEAR THE AREAS, AND ARE ALSO PLACING BLOW RIBBON ALONG THE PATHWAYS TO ENSURE THAT THE MACHINERY STAYS WITHIN THE DESIGNATED AREAS. THESE AREAS WILL BE CHECKED NEXT WEEK ONCE THEY HAVE BEEN COMPL;ETED. |
| 01/24/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
CREW WORKING ON PREPARING FOR THE INSTALLATION OF THE LINES AT THE ENTRANCE OF KOLB ROAD. MOST OF THE STORMWATER CONTROLS GRADER DITCHES HAVE BEEN INSTALLED AT THIS TIME. THE CREW FROM AAA ARE CURRENTLY WORKING ON THE REMOVAL OF VEGETATION ALONG THE EAST END OF THE SITE, NORTH OF THE NEW SOLAR PANEL INSTALLATION. THIS MATERIAL IS BEING PUSH INTO LARGE PILES AND WILL BE REMOVED FROM THE SITE ONCE ALL THE AREAS HAVE BEEN CLEARED. |
| 01/21/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Continued |
CREWS COMPLETED THE INSTALLATION AS POSSIBLE OF THE STORMWATER CONTROLS ALONG THE EAST END OF THE SITE. IN THE AREAS WHERE THERE IS HIGH VEGETATION REMOVAL THEY HAVE STAKED THE CLEARING LIMITS. THE ROPE FOR THESE AREAS WILL BE PLACED ONCE PORTIONS OF THIS MATERIAL HAS BEEN REMOVED, THE REMAINING STORMWATER CONTROLS WILL ALSO BE INSTALLED AT THE SAME TIME. |
| 01/18/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Denied |
MET WITH THE CONTRACTOR TO LOOK OVER THE WORK THAT TOOK PLACE ON FRIDAY. IT APPEARS THAT THEY HAVE CUT GRADER DITCHES IN THE AREAS THAT WILL NOT BE REVEGITATED ALONG THE EDGES OF THE PATHS, AND AAA LANDSCAPING IS WORKING ON TIEING UP SOME OF THE OCOTILLO'S THAT WILL BE TRANSPLANTED ON SITE. REMINDED THE CONTRACTOR NOT TO MAKE ANY CHANGES TO THE SITE WITHOUT HAVE APPROVAL BY THE CONCERNED DEPARTMENTS. |
| 01/14/2011 |
STORMWATER INSTALL OF CONTROLS |
|
Denied |
MET WITH THE CONTRACTOR FOR THE SITE AND LOOKED AT THE PLANS FOR THE SITE, AND DISCUSSED SOME OF THE PROPOSED CHANGES THAT ARE ANTICIPATED TO BE MADE ON THIS SITE DURING CONSTRUCTION. ADVISED THE CONTRACTOR THAT ALL CHANGES THAT ARE EXPECTED NEED TO BE SUBMITTED AT 201 N STONE AND REVIEWED BY THE CORRECT DEPARTMENTS, AND APPROVED PRIOR TO STARTING ANY OF THE CHANGES IN THE FIELD. THEY HAVE ASKED TO HAVE ANOTHER MEETING ON-SITE ON TUESDAY 1/18/2011 WITH JOSEPH LINVILLE IF AT ALL POSSIBLE. I HAVE TRIED TO CONTACT JOSEPH AT THIS TIME BUT HAVE NOT BEEN ABLE TO SCHEDULE HIM FOR THE MEETING ON TUESDAY MORNING. I WILL LET THE DEVELOPER KNOW IF I AM ABLE TO MAKE THIS ARRANGEMENT BY THE END OF THE DAY. WE TOURED THE SITE PRIOR TO MY LEAVING, I HAVE GIVEN VERBAL AUTHORIZATION TO START PLACING SOME OF THE STORMWATER CONTROLS IN THE AREAS THAT DO NOT HAVE ANY VEGETATION. ALL AREAS THAT ARE VEGETATED WILL NEED TO BE APPROVED BY JOSEPH LINVILLE IF THE CHANGES ARE OF SIGNIFICANT SIZE. |