Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2013 | STORMWATER FOLLOW-UP INSP | Approved | SITE WORK IS 90% COMPLETE, LANDSCAPING LEFT | |
| 10/31/2012 | STORMWATER FOLLOW-UP INSP | Continued | 1) CONTRACTOR INSTALLING UTILITIES AND CONSTRUCTING BLDG PAD 2) NO STORM WATER CONCERNS AT THIS TIME |
|
| 10/19/2012 | STORMWATER FOLLOW-UP INSP | Continued | 1) MET WITH SUPERINTENDENT, WALKED SITE. 2) NO SWPPP REQUIREMENT, HOWEVER ROCK ENTRANCE HAS BEEN INSTALLED AND SEDIEMNT CONTROLSMAY BE NEEDED DURING CONSTRUCTION. 3) TRASH ENCLOSURE FOOTING AND BOLLARDS INSTALLED. 4) NO SIGNIFICANT SITE WORK AT THIS TIME. 5) ENSURE ADA ACCESS MEETS CURRENT CODES |