Permit: T08BU01010

Parcel: 10512024D


Addresses:

4040 N ORACLE RD


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T08BU01010

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
09/14/2009 STORMWATER FOLLOW-UP INSP Approved
07/28/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. SITE IS UNDER A SWPPP UNTIL THE SITE IS 100% STABILIZED AND AN NOT IS FILED WITH ADEQ.
06/17/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/05/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
06/04/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
05/08/2009 STORMWATER FOLLOW-UP INSP Continued 1) SELF INSPECTIONS HAVE BEEN PERFORMED AND DOCUMENTED.
2) REMOVE MATERIAL OFF OF PERIMETER SEDIMENT CONTROLS ALONG SOUTH SIDE.
3) TRACKING MUST CONTINUE TO BE SWEPT UP ROUTINELY UNTIL SITE IS PAVED
05/07/2009 STORMWATER FOLLOW-UP INSP Continued SWEEP UP TRACKING OFF OF RODGER ROAD.
04/22/2009 STORMWATER FOLLOW-UP INSP Correction Required 1) CLEAN OUT STORM DRAIN CATCH BASIN LOCATED ON NW CORNER OF AZ BEAUTY BLDG.
2) SWEEP UP TRACKED SOIL OF OFF RODGER RD.
3) PROVIDE SITE DETAIL ON CONNECTION BETWEEN BLDG ROOF DRAINS AND STORM DRAIN PIPING. DETAIL MUST BE STAMPED BY THE ENG OF RECORD AND APPROVED BY THE CITY OF TUCSON.
04/13/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
04/09/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
04/08/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CHANGES
03/26/2009 STORMWATER FOLLOW-UP INSP Continued NO CHANGES
03/23/2009 STORMWATER FOLLOW-UP INSP Continued CONTINUE TO SWEEP DAILY UNTIL SITE IS STABILIZED.
REPLACE PERIMETER CONTROLS AS NEEDED.
NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
03/17/2009 STORMWATER FOLLOW-UP INSP Continued
03/12/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
03/09/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
03/04/2009 STORMWATER FOLLOW-UP INSP Continued NO CHANGES
02/26/2009 STORMWATER FOLLOW-UP INSP Continued SWEEPER IS BEING USED
SEDIMENT CONTROLS ARE MOVED AND ADJUSTED AS NEEDED ON SITE
02/19/2009 STORMWATER FOLLOW-UP INSP Correction Required SWEEP UP TRACKING OFF OF PUBLIC ROADWAY (RODGER RD).
RE-ESTABLISH SEDIMENT CONTROLS AS NEEDED.
02/18/2009 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS AT THIS TIME
02/12/2009 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS AT THIS TIME.
02/10/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
02/06/2009 STORMWATER FOLLOW-UP INSP Continued ENSURE ALL STORM WATER CONTROLS ARE MAINTAINED AND IN PLACE.
CONTINUE TO SWEEP UP TRACKED MATERIAL DAILY.

RAIN FORCAST FOR SUNDAY 2/8/09
02/05/2009 STORMWATER FOLLOW-UP INSP Partial Approval NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/03/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
01/29/2009 STORMWATER FOLLOW-UP INSP Partial Approval NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
01/26/2009 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR NEEDS TO PERFORM SELF-INSPECTION - RAIN DAY NO ACTIVITY - SEDIMENT CONTROLS IN-PLACE
01/23/2009 STORMWATER FOLLOW-UP INSP Correction Required RAIN <.05"/SWEEP UP TRACKED MUD AND DEBRIS
RE-ESTABLISH SEDIMENT CONTROLS AS NEEDED
MAY NEED ROCK ENTRANCE AT EACH WORKING AREA
01/22/2009 STORMWATER FOLLOW-UP INSP Partial Approval NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/21/2009 STORMWATER FOLLOW-UP INSP Correction Required SEDIMENT CONTROLS HAVE BEEN PLACED AROUND THE PERIMETER OF THE SITE AND IN AREAS AROUND STOCKPILED MATERIAL.
ADD FILTER FABRIC TO EXISTING STORM DRAIN SND CLEAN OUT DRAIN AT NE CORNER OF MICHAEL'S. SEDIMENT CONTROLS ARE REQUIRED UNTIL THE DRAINAGE SYSTEM IS REPLACED.
CONTINUE TO PERFORM STORM WATER SELF INSPECTION AND DOCUMENT THEM.
CONTINUE TO SWEEP UP TRACKED MATERIAL OFF OF PARKING AREA ROUTINELY.