Permit: T08BU00699

Parcel: 133040030

Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Permit Number - T08BU00699

Inspection Description - ENGINEERING PRE-CONSTRUCTION

Inspection Status - Approved

Date Description Inspector Results Comments
07/27/2010 ENGINEERING PRE-CONSTRUCTION Approved MET W/ SITE SUPERINTENDENT AND SITE FORMAN TO DISCUSS STORM WATER REQUIREMENTS, AND ALL SITE WORK INVOLVED WITH THIS PROJECT.
1) PROVIDE AN APPROVED COPY OF YOUR SWPPP ON SITEW/ A SIGNED COPY OF YOUR NOI.
2) PROVIDE AN APPROVED COPY OF YOUR GRADING PLAN ON SITE FOR INSPECTION.
3) INSTALL SEDIMENT CONTROLS PER YOUR APPROVED PLAN AND THE DISCUSSION MADE AT THE PRECON.
4) INSTALL A STABILIZED CONSTRUCTION ENTRANCE IN SITE.
5) SWEPP UP ALL TRACKED MATERIAL OFF OF PUBLIC ROADWAYS ON A ROUTINE BASIS.
6) PERFORM PERIODIC STORM WATER MAINTENANCE SELF INSPECTION PER YOUR APPROVED SWPPP.
7) INSTALL A CONCRETE WASH - OUT ON SITE WHEN APPLICABLE.
8) MAINTAIN SEDIMENT CONTROLS THROUGHOUT THE DURATION OF THE CONSTRUCTION.

CALL FOR REINSPECTION FOR ANY QUESTIONS AND/OR CONCERNS.
07/26/2010 ENGINEERING PRE-CONSTRUCTION Continued SPOKE WITH SITE FORMAN ON DEMO WORK BEING DONE ON SITE. HE ALSO STATED THAT CONSTRUCTION WILL START SOON AND A PRE-CON INSPECTION WILL BE CALLED IN.
06/03/2010 ENGINEERING PRE-CONSTRUCTION Continued RIGHT OF WAY WORK BEING DONE, UTILITY TIE-IN WORK.
CONTRACTOR NEEDS TO CALL IN A PRECON MEETING PRIOR TO GRUBBING AND GRADING ON SITE.