Inspection Status: Approved
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2009 | SITE - SEWER | Approved | IVRS - Inspection :* | |
| 01/21/2009 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
| 01/15/2009 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR WILL EXPOSE HORIZONTAL PIPING FOR SEWER FOR VERIFICATION OF GRADE. WILL PROVIDE VISUAL INSPECTION OF SADDLE TAP AND PRESSURE TEST OF PIPING. WATER PIPING WILL BE EXPOSED AT HORZONAL AT BLD. SITE AND TRANSITION FROM COPPER TO PVC AT METER LOCATION |
|
| 01/14/2009 | SITE - SEWER | Denied | IVRS - Inspection : See detailed listing on site.| 999* MANHOLE COVERED, SEWER PIPING NEEDS TO BE EXPOSED ON HORIZONTAL PIPING. HAVE INSTALLER ON SITE FOR NEXT INSPECTION. |
|
| 01/13/2009 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* EXPOSE FUTURE SEWER PER REVISION 1 ABOVE, HAVE INSPECTION, TESTING & VERIFICATION OF GRADE EXPOSE YARD WATER FOR THIS ALSO. |