Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2009 | ENGINEERING - FINAL | Approved | All items complete, as-built drawings will be turned in today. | |
| 10/08/2009 | ENGINEERING - FINAL | Partial Approval | Complete the following items prior to final C of O. Sht. C1.1 1) Install striping per note 49 2) Install all H.C. signs, Min 84" above grade. 3) Address items 3, 19, 21,30, 46 and 50 revise or install per plan. 4) Finish item 31 Sht. C1.2 5) Item 31, place grout or revise plan. 6) Provide revised/as-built plans for grading and site. 7) Provide Eng. Cert for storm system. |
|
| 09/01/2009 | ENGINEERING - FINAL | Partial Approval | OK for TCO, complete grading permit #T07BU01526 prior to final C of O approval. | |
| 08/31/2009 | ENGINEERING - FINAL | Denied | Remove all construction materials and debris from entrance and exit to building. Remove porta-john and temp roll off from active parking and sidewalk areas. Cover all open trench and holes. Install HC parking signs. |
|
| 08/27/2009 | ENGINEERING - FINAL | Not ready for Inspection | Items from previous list not complete | |
| 08/21/2009 | ENGINEERING - FINAL | Denied | Complete the following items prior to Temp C of O. 1) Finish all drive entrances to building 2) FInish all sidewalks to building entrances. 3) Remove all const. debris at entrances and exits to building 4) Remove temp. construction fence along Congress St. 5) Barricade all open trench and holes. 6) Install railing at exit strairs from building. Call for final grading inspection prior to C of O. |