Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2009 | MECHANICAL - INTERMEDIATE | Approved | ||
| 08/24/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) CONDENSATE ON WATER HEATER UNITS-OK |
|
| 08/21/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER HEATER FLUE NOT COMPLETE 2) OK TO COVER ELEVATOR LOBBIES |
|
| 08/19/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) LOWER BASEMENT OK |
|
| 08/07/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 2ND LAYER FIRE WRAP OK, CLEANOUT OK (GREASE DUCT) 2) PROVIDE ACCESS TO TV-406 KITCHEN OK FOR TILES 3) 2ND FLOOR FITNESS ROOM, DAY ROOM, DORM CORRIDOR-OK FOR TILES |
|
| 07/17/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) SECOND FLOOR ATRIUM TO NORTH STAIRWELL-OK TO TILE |
|
| 07/15/2009 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) GROUT FIRE DAMPERS PER MANUFACTURING INSTRUCTIONS |
|
| 06/29/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ROOMS 223,221,219,217,215,213,237 AND 235 OK TO ROCK LIDS |
|
| 06/25/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/22/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* RELIEF DUCT SECOND FLOOR APPARATUS BAY OK TO COVER |
|
| 06/17/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* SOUTH DORM ROOMS -- OK TO ROCK |
|
| 06/11/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* DUCT CONNECTION AT 2ND FLOOR ABOVE APPARATUS BAY NEXT TO DORM #221 |
|
| 06/10/2009 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* CANCELED BY CONTRACTOR - WON'T BE READY UNTIL THIS PM |
|
| 05/12/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* REMOVE SHEETROCK FROM FITNESS ROOM CEILINGS EXPOSE ALL MECH. WORK FOR INSPECTION WE DO NOT INSPECT OFF OF LADDERS AND LIFTS OK FOR SHEETROCK 1ST FLOOR ROOMS 118, 119, CORRIDOR, 2ND FLOOR RESTROOMS |
|
| 05/06/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 05/05/2009 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* OK TO PROCEED |
|
| 05/04/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/21/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1ST FLR. RESTROOMS OK TO ROCK LIDS MECH. ONLY |
|
| 04/15/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* DISTRICT ENERGY WTR THROUGH STATION MAINS PRESSURE TEST OK |
|
| 03/19/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 2ND FLOOR FROM SOUTH END TO COLUMN LINE "E" OK TO INSULATE |
|
| 02/19/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* DUCT OK AS HIGHLIGHTED ON PLANS |
|
| 02/18/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1ST FLOOR M1.3 MED. AND LOW PRESSURE DUCT OK TO WRAP |
|
| 01/20/2009 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* DUCT WORK APPROVED AS NOTED ON INSPECTORS PRINTS |
|
| 12/18/2008 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* S.ELEV. BASEMENT O.S.A OK TO WRAP F.C.7 OSA OK TO WRAP N.ELEV, BASEMENT OSA OK TO WRAP BFC-2, FC-9, OK TO WRAP IN MECH. ROOM AHU-4 OK TO WRAP IN MECH ROOM. |
|
| 09/08/2008 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* |