Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2009 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* 1) ITEMS ON LIST OK |
|
| 10/09/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) ALL LIGHTS ARE INSTALLED OUTDOORS-WE CAN NOW DO OUTDOOR LIGHTING CALCUS PER OUTDOOR LIGHTING CODES AS DISCUSSED 2) OK GATE AND GARAGE CONTROLS 3) FINISH PREVIOUS |
|
| 09/28/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) FINISH MAKE UO PULL BOX MEMORIAL 2) ONLY 2 CONDUCTORS TO A SLIP BOND-PARKING CONTROL 3) FINISH PREVIOUS ITEM MARKED |
|
| 09/18/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) OK SHADE MOTORS AND CONTROLS 2) OK CLIMATIC WIRING, EXCEPT P201 3) FINISH GATE AND GARAGE CONTROL WIRING 4) FINISH WORK AT PARK 5) NO CORDS ABOVE CEILINGS |
|
| 09/17/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/16/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) NEED R CLIPS 2) FINISH STRAPPING 3) LABEL PER 210.5 4) CONTRACTORS TO BE LISTED 5) CONFERENCE 2ND FLOOR VERIFY MOTOR LISTING 6) CORDS NOT ALLOWED ABOVE CEILING 400.7 + 8 7) TIGHTEN FITTINGS |
|
| 09/14/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/11/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/10/2009 | ELECTRIC - FINAL | Partial Approval | FINISH: CLIMATEC WIRING, DOOR MOTORS GARAGE, LOWER LEVEL LIGHTING, BATHROOM COVE LIGHTS, LISTING SHADE MOTORS & CONNECTIONS, CONDUIT ROOM 201, LAST CHECK OF MAIN ELECTRIC ROOM, DRYWALL FIXTURES. | |
| 09/09/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/08/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/03/2009 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/02/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 09/01/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/31/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/28/2009 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 08/26/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* KITCHEN/DINING: 1) FINISH VDV CABLING AND OPEN TILES TO INSPECT OUTSIDE: 1) FINISH COVERS FOR DEVICES 2) GROUND POLES AS DISCUSSED 3) MISSING BOLLARDS WEST GATE 4) SPLICE TO BE FOR WET LOCATION 5) OK ROOMS FOR FINAL 200C,200D,200A,300A,400A & B, 200E AND 200B 6) 210 EXCEPT LIGHTING 7) OK GROUNDING AT GENERATOR-8 OHMS 8) EM KILL LIGHTS NEED 103 AND 100E |
|
| 08/25/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) EM LIGHTING NOT WORKING: FITNESS, APPARATUS BAY, WEST 2) EM LIGHTING NOT WORKING: 2ND FLOOR BREAKROOM, 3RD FLOOR STAIRWELL, BELL TOWER AND CONFERENCE 3) OK P100 AND P200 ABOVE CEILING 4) OK EQUIPMENT LABELING LOWER LEVELS 1 & 2 |
|
| 08/24/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/21/2009 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) OK PVC AT BARRIO MEMORIAL |
|
| 08/20/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) NORTH ELEVATORS: OPEN BOXES, SUPPORT WIRES, VDV ?ING 2) FINISH BATHROOM COVE LIGHTS - BACK ORDERED 3) FINISH WATER HEATER ROOMS OK DORMROOM BATHROOMS EXCEPT LIGHTS OK OUTSIDE PORCHES 2ND FL PATIO'S OK PVC FOR WEST GATES OK PVC SERVERS ACCESS SIDEWALKS REAR GABAGE AREA OK ROOMS FOR FINAL 242,242A,243,203,205,207,208 |
|
| 08/19/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) OK ABOVE CEILING 102,103,P100D AND P200D 2) OK ROOMS FOR FINAL P102,P103,P105 AND P100J 3) RECEIVED GENERATOR REPORT 4) BOND BUSHING LIEBERT UNIT-1ST LL-ACU-01A 5) BOND METAL RACEWAY LIEBERT-250.64(E) 6) VERIFY LIGHTING COMM ROOM B101A 7) FILL UNUSED OPENINGS IN FIXTURES |
|
| 08/18/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) OK ABOVE PANELS, OK LABELING ROOFS AND OK PVC AS MARKED 2) FINISH AS DISCUSSED FOR TOMORROW |
|
| 08/17/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/14/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/13/2009 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 08/12/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/11/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1) NEED MORE INFORMATION FOR SCREEN IN TRAINING ROOM-NOT ON PLANS 2) JUNCTION BOXES TO BE ACCESSIBLE 3) USE APPROVED CONNECTORS WITH SEAL TITE AND TIGHTEN FITTINGS 4) OK ROOMS FOR FINAL 139-152, 121A & 127-132 |
|
| 08/10/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/07/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* | |
| 08/06/2009 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* |