Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/01/2009 | BUILDING ABOVE CEILING | Approved | IVRS - Inspection :* | |
| 08/31/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) REPAIR MONO COAT |
|
| 08/28/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 08/17/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) WAITING ON RFI FOR HARD LID |
|
| 08/14/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) ELEVATOR LOBBY |
|
| 08/13/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) DONE-WATING ON RFI FOR HARD LID |
|
| 08/11/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) 204 A CHECKING ON ACCESS PANEL AND SPRINKLER ABOVE CEILING |
|
| 08/10/2009 | BUILDING ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 08/07/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) APPERATUS FROM DORM ROOMS |
|
| 07/23/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) PENETRATION AT N.E. ELEVATOR FIRE CAULKING OK |
|
| 07/22/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) WORKING ON RATED WALL N.E. CORNER |
|
| 07/21/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 07/15/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) WORKING ON 2ND FLOOR N 1/2 OK TO PROGRESS |
|
| 06/30/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) 2ND FLOOR SOUTH 1/2 NEED TRADE ABOVE CEILING |
|
| 06/24/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* FINISH FIRE CAULKING AT W.VENT SHAFT |
|
| 06/18/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) 1ST FLOOR NORTH 1/2 |
|
| 06/17/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 2ND FLOOR DORM ROOMS OK |
|
| 06/09/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 109, 106 ABOVE HARD LIDS |
|
| 06/03/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) 1ST FLOOR OPEN OFFICES, BREAK ROOM AND KITCHENETTE |
|
| 05/26/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* ROOMS #139-150 T-GRID SYSTEM OK TO SET CEILING TILES IN PROGRESS AREAS |
|
| 05/21/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) 2ND FLOOR BATH HARD LIDS |
|
| 05/14/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) APPERTUS BAY, REMAINING ATRIUM LID AND WALLS 2) MAINTAIN ACCESS OPENINGS |
|
| 04/13/2009 | BUILDING ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1. CORRIDOR LID E TO J LINE 2. 1ST FLOOR BATH HARD LIDS NEED MECH. AND ELEC. |