Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* 1) COMPLIANT PER SCHNEIDER |
|
| 08/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 30' OF NORTH WEST SITE WALL WAITING ON SPECIAL FINAL |
|
| 08/05/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ZONE OF BACK FILL SOUTH OF APPERATUS STEEL-OK 2) LIGHT POLE BALLARDS 3) BARRIO MEMORIAL ART WORK FOUNDATION |
|
| 08/04/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WEST LIGHT POLE CASSIONS |
|
| 08/03/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) MAINTAIN CLEARANCE |
|
| 07/28/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 8' SITE WALL FOOTING WEST SIDE (134) S3.1 2) PROVIDE SPECIAL INSPECTION |
|
| 07/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BARRIO MEMORIAL WALL OK TO CLOSE UP |
|
| 07/23/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STAIRS AT MEMORIAL WALL OK |
|
| 07/17/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WEST RAMP WALL ANT N.E. CORNER |
|
| 07/15/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STAIRS AT N.E. CORNER 2) WEST GENERATOR POD AND S.W. PORCH OVER ZONE OF BACK FILL |
|
| 07/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 07/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) DRIVE AT N.E. CORNER NOT POURED TO PLAN, LOOKED AT BY SCHNEIDER. NOT STRUCTUAL ANY CRACKING SUNDT RESPONSIBLE |
|
| 07/09/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ZONE OF BACK FILL MATTS EAST SIDE AND N.E. CORNER TO APPERATUS BAY NEED RFI FOR SLEEVE IN FOOTING/TURN DOWN |
|
| 07/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) RFI 524 FOR LIGHT POLE CASSIONS EAST SIDE IN SIDWALK 2) NEED FIX FOR PVC IN NE DRIVEWAY FOOTING |
|
| 07/07/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BARRIO MEMORIAL WALL FOOTING OK PER RFI |
|
| 07/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STAMPED RFI FOR HEAD WALL OK 2) ? DISPLAY DETAIL 135 3) CURB WALL WEST OF FIRE FIGHTER ? WALL FOOTING OK |
|
| 07/01/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) COLVENT HEAD WALL PROVIDE BETTER DETAIL |
|
| 06/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) LIGHT POLE CASSION RFI 471 FOR SIZE 2) PROVIDE RFI FROM ENGINEER FOR BOLT DEPTH INTO CASSION, 3 POURED WITHOUT INSPECTION |
|
| 04/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* MEMORIAL WALL FOOTING OK AND EXT. STAIRWAY |
|
| 03/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* KIOSK STAIRS, NE SITE WALL FOOTING OK |
|
| 03/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 03/11/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PLANTER WALLS AT KIOSK |
|
| 03/04/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* KIOSK PLANTER WALL FOOTINGS MISSING 3RD #4 OK TO POUR WITH CALL FROM PHIL |
|
| 03/02/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* E. SITE WALL SOUTH 1/2 |
|
| 02/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* STEEL NOT IN YET |
|
| 01/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* EXCAVATION FOOTING FOR CMU SITE WALL AT PROPERTY LINE AT NE CORNER RFI 12/17/08 SK26 12" MIN. TOP SHELF PER DETAIL |
|
| 01/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GAZEBO FOOTING (139) S2.5 ABOVE TO BE SPECIAL INSPECTED |
|
| 10/29/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GRADE BEAMS A-D/17-19 EXCEPT G-B4 LINE E |
|
| 10/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GB3 17-A TO E |
|
| 10/24/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* OK TO POUR GB2 LINE B AND A.8 9 TO 15.5 WITH SPECIAL INSPECTION |
|
| 10/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. GB2 & GB1 LINES A&B 11 TO 19 VERTICALS NOT INSTALLED 2. GB6 SW CORNER OK TO POUR 3. SPECIAL INSPECTED |
|
| 10/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WW IN PLACE FOR DECK POUR 6.5 TO K |
|
| 10/06/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WORKING ON GRADE BEAM 2 POUR 23 |
|
| 09/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WORKING ON CAISSONS WORKING ON WALL POUR 23 AND 24 |
|
| 08/12/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GB1 FOR ROOM P108 |
|
| 06/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WORKING ON GB 1 & 4 AT C-8 |
|
| 06/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOWER LEVEL GRADE BEAMS GB2 LINE 1 U TO T.5 GB1 K.5 1 TO 2 VERTS 2 #5's 16 O.C TYPICAL MAINTAIN 3" CLEARANCE FOR REBAR |
|
| 05/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TAGGED CF3 CAISSONS CF4 CAISSON MISSING LVERT 1. OK TO POUR COLUMN L-7 2. GRADE BEAM FIX FOR CAISSON M & N LINE 7 STEEL PER RFI |
|
| 05/13/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 05/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* POUR IN PLACE COLUMNS LINE 6 P,M,N MAINTAIN 1/2 CLEARANCE |
|
| 05/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* RFI #172 GB5 6.8 TO 8 LINE C.3 NEXT TO ELEVATOR SHAFT STEEL NOT PLACED TOGGED REPLACEMENT CAISSONS CF1 & CF6 |
|
| 05/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* INFORMATION ONLY |
|
| 05/06/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CF4 & CF1 CAISSONS |
|
| 05/05/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GB2 8 - M TO M5, K.8 TO L, J TO K AND MAINTAIN 3" CLEARANCE |
|
| 05/02/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TAGGED TYPE 1 CAISSONS |
|
| 04/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* S1.1 (32) NOTE 6 JAMB BARS EXTEND FULL HEIGHT OF WALL O TO K.5 ON 5 LINE |
|
| 04/22/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PROGRESS OK G.8/8 INCORRECT LOCATON (OFF 5'2") INSPECTIONS NEED TO BE CALLED DAILY DSD NEEDS TO REVIEW SP. INSP. DAILY |
|
| 04/21/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PROGRESS OK DRILLING & CASES M.5-P.5 ONE SIDE NEED TO FINISH STEEL LINE 5 |
|
| 04/12/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* POURED CAISSONS 8-C & 3 ON LINE 10 SPECIAL INSPECTED |
|
| 04/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* POURED 6 - L & R 9 - L & R 6 - H, 6 - F, 8 - F, R - 6, 8 - A, C - 9 |
|
| 04/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TAGGED CAISSONS TYPE 1 & 6 POURED 6 CAISSONS 4-4 6-M, 6-Q, 9-B.5, 9-G.5, 8-6, 8-D SPECIAL INSPECTED |
|
| 04/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* POURED 6 CAISSONS G-5, C-6, F-9, R.5-6, N-6, 9-A SPECIAL INSPECTED TAGGED TYPE 6 CAISSON REBAR |
|
| 04/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LOOKED AT AND TAGGED TYPE 6 & 5 CAISSONS |
|
| 04/02/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* POURED 5 CAISSONS 5 - M, L, K, I, H 6-P SPECIAL INSPECTED TAGGED TYPE 5 & 6 REBAR |
|
| 04/01/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CAISSONS POURED 5 AT Q, P, N TYPE 5 & TYPE 6 CAISSONS REBAR TAGGED P-6 WILL HAVE COLD JOINT AT TOP 6" SPECIAL INSPECTED |
|
| 03/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 5-F CAISSON POURED S3.0 (102) SPECIAL INSPECTED |
|
| 03/27/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LOOKED AT AND TAGGED TYPE 6 CAISSONS REBAR CAGES |
|
| 03/26/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LOOKED AT TYPE 6 CAGES (10) INITIALED AND TAGGED SPECIAL INSPECTED |