Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2009 | ENGINEERING - FINAL | Approved | ||
| 04/09/2009 | ENGINEERING - FINAL | Partial Approval | 1- Address ADA access from R.O.W. 2- Down spout needs to be scupped under sidewalk. |
|
| 04/08/2009 | ENGINEERING - FINAL | Denied | ACCESS FROM ROW MEETS ADAAG/ANSI A 24' PAAL IS MAINTAINED AT ENTRANCE INSTALL WHEEL STOPS AT PARKING SPACES TO ALLOW 4' ACCESS WAY, AS SHOWN ON YOUR APPROVED SITE PLAN. |
|
| 09/10/2008 | ENGINEERING - FINAL | Not ready for Inspection | MET ONSITE WITH THE CONTRACTOR THE DRIVEWAY HAS BEEN RELOCATED TO MATCH THE EXISTING DEPRESSED CURB/DRIVEWAY LOCATION. THERE IS A CONCERN WITH THE ACCESSIBLE ROUTE FROM THE ROW TO THE WEST SIDE OF THE BUILDING. INSPECTION RESULTS ARE AS FOLLOWS: ADDRESS CHANGE IN LOCATION OF DRIVEWAY AND ENSURE A 24' PAAL IS MAINTAINED ADDRESS ELEVATION DIFFERENCES FOR ADA/ACCESSIBLE ROUTE AT WEST SIDE OF SITE/BUILDING *ADDRESS SITE DIFFERENCES ON PLAN AND HAVE APPROVED BY THE CITY OF TUCSON |