Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
09/04/2008 EXCAVATION/LAYOUT REBAR & ZON Approved
07/14/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F2 - SPREAD FOOTING FOR DOUBLE DOOR @ LINE 3 EAST SIDE
04/10/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SOUTHSIDE MECH YARD SCREEN WALLS AND SOUND ROOM STAIR FOOTINGS OK
04/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU COLUMN FOOTINGS (8) @ SOUTHEAST EXTERIOR OF AUDITORIUM BLDG.
03/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EASTSIDE DOUBLE RAMP WALL FOOTING REINFORCEMENT STEEL OK TO POUR
03/19/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU WALL FOOTING AT EAST BUILDING OK
09/25/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU WALL FOOTING @ THE WEST SIDE GRID LINES
A/2 TO 4 W/DOOR OPENING
09/18/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
BLDG. FOOTINGS @ GRID LINES B/2.5 TO 6 - 6/B TO K
J/3.5 TO 6
K/6 TO 5 - 5/K TO L - L/5 TO 3 - 3/K TO L - K/2 TO 3
09/01/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REBAR @ FOOTING @ LINES 1 TO 2 & B TO K AND EXISTING TO 1 LINE & A TO K W F1, F2 & F6 CMU WALL/COLUMN FOOTING
08/10/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) LINE ZZ/0-1 DETAIL 123 OK WHEN RETAIN VE?TS ADDRED 8" ON CENTER
2) LINE A & LINE B 1-2 (RIGGING PIT) OK
3) LINE 2/A-G WITH ? PIT OK
08/09/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
LINE 2/A-G
F2 ORCH PIT
LINE A & B 1-2

1. CLARIFY WITH ENGINEER VERTS @ LINE B/1-2
16" PER DETAIL 106 OR 32" PER TYPE SCHEDULE
2. CLARIFY F.C FOOTING NON-STAGGERED LAP SPLICE IN FOOTINGS