Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T07BU02606
Inspection Description - GRADING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/20/2010 | GRADING - FINAL | Approved | FINAL GRADING APPROVED, SITE HAS BEEN SUBSTANTIALLY COMPLETED PER THE APPROVED PLANS | |
02/19/2010 | GRADING - FINAL | Denied | 1) SITE WORK NOT COMPLETED - ALL SITE WORK NEEDS TO BE 100% COMPLETED PER THE APPROVED PLANS PRIOR TO FINAL APPROVAL BY ENGINEERING TO INCLUDE ALL PUNCH LIST ITEMS IDENTIFIED ON PHASE I OF THE PROJECT. 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENG. OF RECORD STATING THAT THE STORM DRAINAGE SYSTEM CONSTRUCTED WAS COMPLETED IN ACCORDANCE WITH THE APPROVED PLANS. 3) PROVIDE AN AS-BUILT DRAWING FOR FINAL INSPECTION. 4) REMOVE ANY AND ALL CONSTRUCTION EQUIPMENT, DEBRIS, AND MATERIALS PRIOR TO FINAL APPROVAL BY ENGINEERING. |
|
10/15/2009 | GRADING - FINAL | Denied | Site not ready | |
01/20/2009 | GRADING - FINAL | Denied | SITE WORK NOT COMPLETED, CHANGES MADE TO APPROVED GRADING PLAN, NEED APPROVAL AND PLAN SHOWING CHANGES. |