| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2008 | GRADING - FINAL | Approved | Contractor provided letter for site cert. | |
| 04/02/2008 | GRADING - FINAL | Partial Approval | Met with Jack on site, went over PAAL width. | |
| 10/31/2007 | GRADING - FINAL | Continued | Met Bob on site, went over changes to sidewalk and HC ramps northside of building. | |
| 10/26/2007 | GRADING - FINAL | Continued | Met with Bob site super on site. Bob needs to contact Right-of-way inspection for sidewalks and ramps in right-of-way. Contractor needs to make minor changes to sidewalk and ramp on north side of building. | |
| 07/12/2007 | GRADING - FINAL | Correction Required | Issued correction notice. Contractor stock piling material outside of grading limits. Contractor needs to: 1- Stop all work outside grading limits. 2- Obtain stock piling permit or new grading permit for all work outside of grading limits. 3- Provide SWPPP showing all installed controls outside of grading limits. Contractor has 14 days. If no action takes place will issue a notice of voilation or stop work order. Spoke to site super in re-gards to. |
|
| 07/11/2007 | GRADING - FINAL | Correction Required | Contractor grading and stock piling outside grading limits. Contractor said there was an approved set of drawing for the work. I check with Jason Green and could find no approved drawings. Will issue a correction notice. |