Inspection History Details
Inspection Status: Approved
Inspection History: INSP - AST/UST
Case Number - T06FR02250
Inspection Description - INSP - AST/UST
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/12/2006 | INSP - AST/UST | Approved | Final done and contractor will send me copy of electrical final. Verified electrical inspection with R.Hollander, issue with compressor needs to be rectified but the rest of the station is OK. | |
08/08/2006 | INSP - AST/UST | Approved | Secondary piping inspection @ 5 psi. Advised that he will need electrical final prior to fire final. | |
08/03/2006 | INSP - AST/UST | Approved | Primary piping inspection @ 50 psi, vapor recovery @ 5 psi for 2 hrs. OK to start on secondary piping. | |
07/18/2006 | INSP - AST/UST | Approved | Passed tank tightness pre-burial test, held pressure for 2 hours @ 3 psi. |