Permit: T06CM06423

Parcel: 13320129C


Addresses:

6300 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
11/17/2008 ENGINEERING - FINAL Approved AS-BUILT PLANS WERE RECEIVED AND APPROVED BY LAITH ALSHAMI
11/05/2008 ENGINEERING - FINAL Partial Approval OK FOR TCO, SEE PREVIOUS NOTES
10/24/2008 ENGINEERING - FINAL Partial Approval OK FOR TCO PENDING COMPLETED AS-BUILT AND FINAL GRADING APPROVAL
10/20/2008 ENGINEERING - FINAL Not ready for Inspection SEE PREVIOUS NOTES
ALSO NEED (2) SCUPPERS, (1) HANDRAIL, CORRECT PONDING WATER.
10/16/2008 ENGINEERING - FINAL Not ready for Inspection OK FOR TEMPORARY C OF O FOR FURNISHING AND STOCKING ONLY.
1. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR GRADING PERMIT #T06BU02875 IS COMPLETED AND APPROVE.
2. PROVIDE A LETTER OF CERTIFICATION FROM AN ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT, THE DRAINAGE AND THE R/D BASIN ARE CONSTRUCTED TO THE APPROVED PLANS AND FUNCTION AS DESIGNED.
3. COMPLETE ALL SITE WORK.
4. CALL IN FINAL GRADING INSPECTION
5. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS.
10/02/2008 ENGINEERING - FINAL Partial Approval OK FOR TEMPORARY C OF O FOR FURNISHING AND STOCKING ONLY.
1. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR GRADING PERMIT #T06BU02875 IS COMPLETED AND APPROVE.
2. PROVIDE A LETTER OF CERTIFICATION FROM AN ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT, THE DRAINAGE AND THE R/D BASIN ARE CONSTRUCTED TO THE APPROVED PLANS AND FUNCTION AS DESIGNED.
3. COMPLETE ALL SITE WORK.
4. BARRICADE ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURING TO PREVENT NON-CONSTRUCTION TRAFFIC.
5. MAINTAIN SAFE INGRESS/EGRESS TO SPEEDWAY AND WILMOT.
08/20/2008 ENGINEERING - FINAL Partial Approval OK FOR TEMPORARY C OF O FOR SALES OFFICES ONLY.
PERMANENT C OF O NOT TO BE GIVEN UNTIL ALL SITE WORK IS COMPLETED AND THE FINAL GRADING INSPECTION IS COMPLETED AND APPROVED.
1. MAINTAIN PEDESTRIAN AND VEHICLE ACCESSABILITY FROM SPEEDWAY TO THE BUILDING.
2. BARRICADE ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING TO PREVENT PUBLIC ACCESS.
08/18/2008 ENGINEERING - FINAL Denied NOT READY
1. PROVIDE SAFE VEHICLE PARKING AND ACCESS FROM SPEEDWAY TO BUILDING.
2. PROVIDE SAFE PEDESTRIAN ACCESS FROM SPEEDWAY TO BUILDING.
3. CLEAN UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS.
4. BARRICADE ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING TO PREVENT PUBLIC ACCESS.