Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/09/2008 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 10/01/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* WAITING ON PLAN REVISIONS |
|
| 09/29/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* PLAN REVS. ALSO, HAVE MECHANICAL INSP. OF LAUNDRY AREA |
|
| 09/26/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | GAS PRESSURE TESTING COMPLETE. WILL SOAP TEST REGULATORS. |
|
| 09/22/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* GAS PIPING TO LAUNDRY NOT PER PLAN AS NOTED ON 3/13/08 CORRECT PIPING, REDLINE PLANS FOR INSPECTION PROVIDE REV. MAKE CONN TO BUILDING C AND TEST FOR FINAL PRESSURE TEST. |
|
| 09/19/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* GAS TEST AT POOL FIRE PLACE OK |
|
| 09/17/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 09/15/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* WRAPS ON GAS PIPING AT SERVICE OK TO COVER |
|
| 09/12/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* YARD PIPING, OK TO COVER PE, WRAP IRON PIPE |
|
| 09/11/2008 | PLUMBING - GAS PRESSURE TEST | Cancelled | ||
| 08/15/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* BARBEQUE PIPING AT KIT. OK PER REDLINES ON P5.1 PROVIDE ACCESS TO SOV AT FINAL AND PLAN REVISION GAS TO BARBEQUE AT TRELLIS OK GAS TO POOL LIGHTS NOT SHOWN ON P6.5 |
|
| 06/27/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* GAS TO GAS LIGHTS IN CACHE OK |
|
| 06/26/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 06/23/2008 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* GAS PIPING & REGULATOR LOCATIONS NOT PER PLAN TEST MED. PSI PIPING TO 60 PSI AND LOW PRESSURE PIPING TO 10 PSI |
|
| 04/11/2008 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
| 03/13/2008 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* |