Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/17/2008 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 08/04/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SEC. B EMPLOYEE RM ROUGH SOIL W/TEST OK |
|
| 05/06/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* GREASE INTERCEPTOR INSTALLED PER REDLINE ON P-1-1-3 TEST OK. SEWER HAS NOT BEEN APPROVED. AUTHORIZATION FROM PC IS REQUIRED FOR CONNECTION TO SEWER. |
|
| 03/12/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST FOR 4" FROM 6" BUILDING SEWER TO CAN WASH AREA PER PO.1.1 YELLOW PAGE OK 1. WILL NEED END OF LINE CLEANOUT & TRANSITION TO APPROVED MATERIAL FOR SUN EXPOSURE. 3/4 WATER TO SAME OK |
|
| 02/20/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SEC A GW OK TO COVER REDLINE CHANGES |
|
| 02/19/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SANITARY PIPING BUILDING A - OK TO COVER |
|
| 11/06/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* - OK FOR CONCRETE SEC. C BETWEEN COLS. 14-19 - SOIL PIPING SEC. C OK TO COVER AFTER REMOVING LARGE CHUNKS. - BACKFILL SHALL BE DONE PER UPC SEC. 315.4 USE CLEANFILL HAND PLACED |
|
| 11/05/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* TOM @ 602-725-0607 TRUNK LINE, CORRIDOR 2119 OK COMPLETION OF PIPING AT SE CORNER OF CORR. 2121 OK |
|
| 11/01/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/26/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 4" GW FROM EXTERIOR TO INITIAL P1.13 PLUMBERS MINI PLAN WATER TEST OK WATER TEST UNITS # 1/2 1138 NORTH THRU 1134 & 1185 INITIALED ON P1.13 MAKE REPAIR 3" 45 DEG. AT UNIT 1185 |
|
| 10/25/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* UNIT #1179 WATER TEST OK FROM UNIT #1180 EAST TO UNIT #1139 WATER TEST OK |
|
| 10/24/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST FROM UNITS 1142 & 1179 WEST OK EXCEPT UNIT 1177 |
|
| 10/23/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST COMPLETION OF BUILDING D UNDERGROUND OK |
|
| 10/18/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST BUILDING D FROM UNIT 1163 WEST TO 6" JUNCTION FROM SOUTH AT UNIT 1159 OK |
|
| 10/17/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
| 10/11/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* REPAIR SEC. B 8" COUPLINGS UNDER TEST OK TO COVER HCS SEC D, CONNECTION MADE OK HAVE NOT YET RECEIVED AUTHORIZATION TO DISCHARGE CONTRACTOR WAS TOLD NOT TO CONNECT |
|
| 10/10/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SEC. B EAST SIDE OK. RETEST MAIN SEC. D FROM SPLIT AT RM 1169 NORTH TO 1167 |
|
| 10/09/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/09/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WEST HALF OF BUILDING B RETEST ON UNDERGROUND DWV OK |
|
| 10/05/2007 | PLUMBING - ROUGH, SOIL | Cancelled | ||
| 10/04/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/03/2007 | PLUMBING - ROUGH, SOIL | Cancelled | ||
| 10/02/2007 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* SEC. B - LARGE QUANTITIES OF BRANCH PIPING AND COMPLETE BATHROOM GROUPS OF PIPING HAVE BEEN REMOVED AND REINSTALLED - UNCOVER THESE AREAS FOR REINSPECTION AND RETEST |
|
| 10/01/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SEC. D SOUTH HALF TO ELEVATOR LOCATION OK |
|
| 09/28/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/24/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* LAUNDRY DRAINS RM 2106 OK TO COVER CORRECT TIE IN POINT PROVIDE CO PER PLAN |
|
| 09/21/2007 | PLUMBING - ROUGH, SOIL | Cancelled | ||
| 09/18/2007 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* NEW PLUMBING CONTRACTOR IS BILL SISSON LAUNDRY RM 2106 PLAN SHOWS 6" TO TD SUPPORT & SHADE PIPING W/CLEAN FILL ALL FIXTURES REQUIRE A VENT, INSTALL PER PLAN TEST ON 2" RISER OK WRAP AND SUPPORT PIPING IN FOOTING |
|
| 09/07/2007 | PLUMBING - ROUGH, SOIL | Cancelled | IVRS - RI canceled | |
| 09/07/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SEC B ALL BRANCH PIPING OK EXCEPT FOR LAUNDRY 2106, 2108 AND ELEVATOR SUMP AREAS |
|
| 09/05/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/04/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* - BRANCH PIPING RMS 2114-1116 OK TO COVER - PROVIDE CONTINUOUS SUPPORT AND UNIFORM SLOPE IN ALL AREAS |
|
| 08/30/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SECTION B ALL MAIN TRUNK LINES OK TO COVER BRANCH PIPING OK EXCEPT ALONG EAST SIDE MAIN; BRANCH PIPING NOT YET INSTALLED. REDLINE CHANGES FOR TROUGH DRAINS. |
|
| 08/29/2007 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* RETEST, WATER IN TRENCH. REMOVE LOOSE DIRT AROUND FITTINGS. REMOVE ROCKS OVER 3/4" CORRECT SLOPE ON BRANCHES PROVIDE TRAP AND VENT FOR TRENCH DRAINS PER SEC. 1001 PROVIDE TRAP SEAL PROTECTION REDLINE CHANGE. PROVIDE APPROVED PLAN REVISION. |
|
| 08/28/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST FROM BUILDING EXTERIOR 8" TRUNK BLD DRAIN TO MY INITIAL AT UNIT 1107, BRANCH PIPING FOR UNITS 1107, 1108, 1109, 1110 MINUS STOOL BRANCH PIPING UNITS 1118, 1119 |
|
| 08/27/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* TEST TO BE IN PLACE AT TIME OF INSPECTION |