Permit: T06CM06423

Parcel: 13320129C


Addresses:

6300 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
10/17/2008 BUILDING PRE-SLAB Approved IVRS - Inspection :*
08/22/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PASS THROUGH (CONSTRUCTION ACCESS)
BETWEEN BLDG. B & C -- OK TO POUR
08/07/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PASS THRU SLAB-OK TO POUR
03/27/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
2ND FLOOR SLAB; 1ST FLOOR NE PATIO; ROOMS 2167, 2168 -- OK TO POUR SLAB
03/17/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BUILDING "A" - 1ST FLOOR - OK TO POUR
02/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
3RD FLOOR N. ELEVATOR AREA, ABOVE ROOMS 2168, 2167
OK TO POUR
01/22/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
NORTH STAIRWELL AND ELEVATOR EQUIPMENT FLOOR
OK TO POUR
11/27/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1) PARTIAL IN-POUR AT SOUTH ELEVATOR LINE T/15
2) OK TO POUR
11/26/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
IN-POUR @ LINES H/17 TO I/17; L/17 TO L.5/17 - OK TO POUR
11/20/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
IN POURS @ C-2 & C-3
ELEVATOR AREA @ B-2 & C-3
PARTIAL - OK TO POUR
11/19/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
POUR BACK
SLAB @ C1 & C2; D1 & A EAST SIDE - POUR BACK
OK TO POUR
11/15/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BLDG C-3 POST TENSION SYSTEM; SLAB @ D-1 TO D/2
OK TO POUR
11/13/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1) BLDG C-2 POST TENSION SYSTEM-OK TO POUR
11/08/2007 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
11/07/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BLDG "C-1" - PRETENSION CABLE SYSTEM - OK TO POUR
11/05/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BLDG D-2 POST TENSION SYSTEM - OK TO POUR
10/31/2007 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
10/25/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BLDG "D" - SW CORNER - POST TENSION SYSTEM
OK TO POUR
10/23/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BLDG "B" LINE: A/19.5 TO E/19.5 -- OK TO POUR
10/15/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
EAST PORTION OF BLDG "B" - POST TENSION SYSTEM
(SPECIAL INSPECTION) OK TO POUR
10/12/2007 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
WILL RECALL
10/11/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
POST TENDON PLAN - OK TO POUR FOR BLDG "B" AS
PER PAGE S2.10 -- OK TO POUR - SPECIAL INSPECTED