Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2007 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 09/10/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 16 - EXTERIOR CANOPY FOOTINGS - 4 - DOUBLE CANOPY FOOTINGS & 12 - SINGLE CANOPY FOOTINGS AS PER SHEET S2.1 DETAIL #12 & #13 |
|
| 08/14/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REMAINING GRADE BEAMS OK |
|
| 08/10/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GB 1, 2, 3, 8 OK/AND 4 OK TO PLACE WHEN SP INSP VERIFIES |
|
| 08/09/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/07/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 8 CAISSONS E BLD A 5 CAISSONS N BLD A |
|
| 08/06/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* JOB SHUT DOWN DUE TO RAIN |
|
| 08/03/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BLD 1 WEST CAISSONS ALONG WEST SIDE (12-13) AS NOTED BY CARL @ PATT/EVANOFF OK TO PLACE SATURDAY CAISSONS AS NOTED BY EARL |
|
| 07/31/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* THIS INSPECTION COVERS ALL INTERIOR CAISSONS FOR BLD. 1 (WEST) IN ACCORDANCE WITH SPECIFIC DETAILS AND LAYOUT S1.1, S2.1, S.00 |
|
| 07/30/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 07/26/2007 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
| 07/20/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 39 REIF. CAISSONS THIS INSPECTION COVERS REINFORCING STEEL FOR CAISSONS FOOTINGS IN COMPLIANCE WITH RFI BY JAMES D. HART/CIVIL ENGINEER ON 7/18/07 AND APPROVED PLANS DETAIL 3 ON SHEET S2.1 THE FOLLOWING REINFORCING IS FOR CAISSONS PERIMETER AND INTERIOR. |
|
| 07/18/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE SPECIFIC DETAIL FOR TIES CONNECTIONS (HOOK'S) IN COMPLIANCE WITH CROSS SECTION A FOR REINFORCING ON CAISSONS (OR PROVIDE RFI BY ENGINEER AND APPROVED BY DSD CITY OF TUCSON PLANS EXAMINER) MUST CALL OR REQUEST INSPECTION WHEN SETUP REINFORCING STEEL IN DRILLED SHAFT PRIOR TO POUR |
|
| 07/17/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSONS FOR EAST BUILDING OK PER REVUE OF SPECIAL INSPECTION REPORTS. OK TO CONTINUE WORK. NO FUTURE WORK MAY BE COVERED WITHOUT EXPLICIT APPROVAL BY A CITY OF TUCSON DSD INSPECTOR. | |
| 07/11/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* - MUST CALL FOR INSPECTION PRIOR TO COVERING OR CONCEALING WORK (CAISSON). - NOTICE OF VIOLATION IN ACCORDANCE WITH THE SECTION 113.2 & 109.3.1 OF IBC 'O6 - STOP WORK ORDER BY SEC. 114.1 & 2 THIS STOP WORK ORDER IS FOR THE PURPOSE PROVIDE INFORMATION (SPECIAL INSPECTIONS REPORTS) ABOUT COVERING WORK (PLACEMENT OR POUR CONCRETE ON CAISSON FOUNDATION FOR BLDG. 2 IN ACCORDANCE WITH SHEET C2 ON APPROVED PLANS. - CONTACT STRUCTURAL PLANS EXAMINER, BUILDING OFFICIAL 201 N STONE AV; TUCSON AZ 85726 |