Permit: T06CM05804

Parcel: 13317064B

Inspection Status: Approved

Inspection History: PLUMBING - GAS PRESSURE TEST

Date Description Inspector Results Comments
05/16/2008 PLUMBING - GAS PRESSURE TEST Approved IVRS - Inspection :*
WELDER CERTS OK
LOW PSI TEST & HANGERS OK
INSTALL REGULATORS
RECALL FOR GAS TEST FINAL
05/14/2008 PLUMBING - GAS PRESSURE TEST Denied IVRS - Inspection :
See detailed listing on site.| 999*
LOW PSI TEST AND SUPPORTS PREVIOUSLY NOTED. ALSO, PROVIDE WELDER CERTIFICATION. NEED PLAN REVISIONS, AND ALL EQUIPMENT INSTALLED FOR GAS CLEARANCE. ALSO, NEED MECHANICAL APPROVAL
04/28/2008 PLUMBING - GAS PRESSURE TEST Partial Approval IVRS - Inspection :*
60+ PSI TEST ON 4" FROM METER LOCATION TO CAPPED VERTICAL STUBS AT 1" ABOVE ROOF LEVEL AND 3' ABOVE PENTHOUSE FLOOR LEVEL PER REDLINE ON SITE FOR 2 PSI SYSTEM ONLY. PROVIDE TESTING ON INCHES SYSTEM. THIS SYSTEM WILL REQUIRE REVISED CITY APPROVED PLAN. PROVIDE HANGERS AT CHANGES OF DIRECTION AND ELEVATION.
04/25/2008 PLUMBING - GAS PRESSURE TEST Not ready for Inspection IVRS - Inspection :*