Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - CABLE DROP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2008 | ELECTRIC - CABLE DROP | Approved | IVRS - Inspection :* | |
| 09/10/2008 | ELECTRIC - CABLE DROP | Not ready for Inspection | IVRS - Inspection :* | |
| 09/09/2008 | ELECTRIC - CABLE DROP | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. RACEWAYS TO EXTEND NO MORE THAN 3" INTO BOTTOM OF SWITCHGEAR 2. BOND METAL RACEWAYS 3. NEED PROTECTIVE BUSHING FOR WIRES #4 & LARGER THIS INCLUDES SERVICE CONDUCTORS IN RIC 4. ANCHOR SWITCHGEAR TO PAD PER INSTRUCTIONS 5. PROVIDE LETTER OF TORQUE 6. REMOVE EXCESSIVE ANTI-OXIDATION COMPOUND 7. PROTECT WIRES FROM SHARP EDGES 8. NEED TO POST BOND |
|
| 09/08/2008 | ELECTRIC - CABLE DROP | Not ready for Inspection | IVRS - Inspection :* | |
| 08/25/2008 | ELECTRIC - CABLE DROP | Partial Approval | IVRS - Inspection :* OK U.G ALONG NORTH WALL OUTSIDE OF BUILDING |