Permit: T06CM03151

Parcel: 11202003D

Inspection Status: Approved

Inspection History: SHEET ROCK NAILING

Permit Number - T06CM03151

Inspection Description - SHEET ROCK NAILING

Inspection Status - Approved

Date Description Inspector Results Comments
09/04/2007 SHEET ROCK NAILING Approved IVRS - Inspection :*
08/10/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
08/01/2007 SHEET ROCK NAILING Partial Approval ELEVATOR ROOM OK
07/30/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOM 120 OK
07/27/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOMS 136, 138 THRU 146, 230, 231, 233, 234, 236, 237, 122, 209 THRU 211
07/24/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
CORRIDOR 219
1ST LAYER ROOM 223-228, 201-211 OK
WEST LID ON CANOPY OK
07/20/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
CORRIDORS 2ND FLOOR
07/18/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOMS 223 THRU 227
2ND FLOOR CORRIDORS OK
07/16/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOMS 126, 127, 124, 125, 123 OK CORRIDOR EAST POD
EAST HALF
07/11/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOM 228 BATHROOM
06/26/2007 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
INCOMPLETE
06/21/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
2ND FLOOR RESTROOM ABOVE CEILING OK
06/20/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1ST FLOOR OFFICES OK
06/14/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) EXTERIOR WALL SOUTHWEST POD
06/11/2007 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
INCOMPLETE
06/04/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ROOM 227, 228, 225, 226, 223, 224 & NORTH EXTERIOR WALL OF EAST WING
05/21/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1ST LAYER ROOM 126
2ND LAYER WEST POD
05/18/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
NW & WEST PORTION -- 1ST LAYER ON CEILING
FOR 1 HOUR RATING -- MAIN ENTRY CEILING -- 2 @ LAYERS
05/16/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
2ND LAYR LID ON 2ND FLOOR EAST POD
05/14/2007 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1ST LAYER G.L B.5 TO EAST END
05/11/2007 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*

INCOMPLETE