| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2008 | ENGINEERING - FINAL | Approved | Contractro installed handrail. | |
| 04/21/2008 | ENGINEERING - FINAL | Partial Approval | Contractor needs to install handrail on new ramp | |
| 04/14/2008 | ENGINEERING - FINAL | Denied | Ramp not in compliance with ADA or ANSI. Ramp is 12% Side wings are 18% Approved drawings call for all to be 8% (12 to 1) |
|