Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 12/18/2006 | PLUMBING - FINAL | Partial Approval | ONLY ISSUES REMAINING ARE: 1. INSTALLATION INSTRUCTIONS FOR NEUTRALIZATION TANKS 2. TERMINATION OF ROOF DRAINS 3. CHECK VALVE INSTALLED BETWEEN EXPANSION TANK AND WH IS NOT PER PLAN AND PREVENTS THE EFFECTIVENESS OF THE EXPANSION TANK. I SEE NO HAZARDS THAT WOULD PREVENT A TCO |
|
| 12/14/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. PLAN REVISION FOR AAV AT P-6 2. CHECK AT RECIRC PUMP 3. NEUTRALIZING TANK INSTALLATION INSTRUCTIONS FOR P-6 (P-10) 4. ROOF DRAINS MISSING STRAINER. |
|
| 12/13/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* - PROVIDE REVISION FOR USE OF AAV'S AT P-6 LOCATIONS AS REQUESTED ON 9/29 - PROVIDE P2 DETAIL FOR RECIRC PUMP OR MANUFACTURES INSTALLATION INSTRUCTIONS. - PROVIDE DETAIL FOR NEUTRALIZING TANK PROVIDE PLUMBING SPECS PROVIDE ACCESS TO ROOF |