| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/11/2007 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* COMPRESSOR AND AIR DRYER COMPLETE |
|
| 12/19/2006 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection :* 1. TRAILER PNL OK, PNL LE-OK 2. TRAILER TRANSFORMER REQUIRES A WP COVER BEFORE RELEASE. 3. HIGH BAY LIGHT FIXTURES VERIFIED OR WEIGHING 21 POUNDS EACH OK ON BOX. 4. ALL OUTSIDE POLE BASES OK 5. ALL INSIDE LIGHTING OK 6. PNL HA CIRCUITRY OK 7. JUST NEED COMPRESSOR HOOKED UP |
|
| 12/18/2006 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. SES OK FOR POWER CLEARANCE 2. CIR'S LA 1 & 3 OK, LIGHTING BATHROOMS OK LC 32, 34 OC 3. WH OK, TOOL RM OK, OFFICE AC OK 4. OFFICE OK -- STRAP MC FAN MOTOR, POWER LC 36, 38.40 OK 5. VERIFY HIGH-BAY LIGHTING 50 LBS OR LESS 6. OUTSIDE MAIN BLD. LIGHTING - 90 W LPS OK, HOUR O/S DOOR LTS OK, OK TO ENERGIZE ABOVE AS LISTED. 7. GFI TEST OK & SUBMITTED 8. LETTER FROM ELECT ENG ON PRIMARY FEEDERS SUBMITTED & OK 9. TORQUE LETTER FROM ELECT. CONTRACTOR SUBMITTED & OK |
|
| 12/15/2006 | ELECTRIC - FINAL | Denied | 1. POWER HAS ALREADY BE CONNECTED & IS ENERGIZED BY TEP. 2. GFI TEST OK 3. MBJ - INSTALLED AT 2W GEAR NOW 250VCC OK 4. 400 AMP FUSE FOR MCC-2 OK 5. JUST NEED FAX ON SERVICE ENTRANCE CONDUCTORS APPROVAL TO CLEAR TEMP POWER ONCE POWER RELEASED - DO NOT ENERGIZE ANY CIRCUITRY FROM ANY PANELS OR DISCONNECTS UNTIL WORK IS INSPECTED. |
|
| 12/13/2006 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* "SW GEAR" 1. GFI TEST OK 2. TORQUE AS PER MANUFACTURE REQMT FROM ELECT CONTRACTOR NEEDED. 3. #4 CU UFER OK, 4/0 TO WATER & BLD STEEL OK 4. MAIN BONDING JUMPER IN SW GEAR TO BE 250 MCM PER PLAN 5. PLAN DOES NOT SHOW MAIN FEED TO SW GEAR FROM TRANS (TEP) SB 4 (3-750 MCM 1-4/0 NEU) PLEASE VERIFY. 6. ADDRESS MAIN SW GEAR (OUTSIDE) 7. ISOLATE FEEDERS AT BOTTOM OF GEAR FROM GEAR STRUCTURE - BOTTOM 8. DIS HA - OK, DIS MCC -A- OK, MCC-B INSTALL NEW FUSE ON PHASE BROWN SAME AS PHASE O,Y, DIS FOR LA & LB OK, DIS FOR LC & LD PLAN CALLS FOR LPS FUSE. 9. PN HA - USE BUSHING ON #4 CONDUCTOR & OVER ENTERING CABINETS. 10. MCC-A OK 11. ALL CONDUITS ENTERING ENCLOSURES TO BE SUPPORTED WITHIN 3' 12. TRANS LA & LB OK PNL LA & LB OK 13. TRANS LC & LD OK 14. PROVIDE PERMITS FOR OTHER WORK ON SITE CONTROL WIRING INTO PNL? |
|
| 11/28/2006 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. A BOND FOR TEMP POWER FOR TEST IS NEEDED. 2. LABEL EQUIPMENT ON OUTSIDE COVERS 3. TERMINATE ALL CONDUCTORS 4. GROUNDING ELECTRODE CONDUCTORS (TRANSFORMERS) TO BE SIZED PER 250.66 - 250.30 (A)(2) 5. CONDUCTORS TO BE IN SAME SECTION AS TERMINATION 408.3 (A)(3) 6. NEED GFI TEST PER 230.95(C) |