Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/02/2007 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 06/18/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/14/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) OK TEKO ROOM, NOC ROOM, PANTRY, BATHROOMS, SWITCHGEAR ROOM AND LOADING DOCK 2) INSTALL K.O. SEALS IN SMOKE DETECTOR BOXES IN MER FLOOR 3) NEED REVISED DRAWINGS FOR BATTERY ROOMS 4) LABEL ALL PANELS, DISCONNECTS AND INSTALL PANEL DIRECTORIES 5) FLEXIBLE POWER CABLE USED IN BATTERY ROOMS NEEDS TO TERMINATE IN LUGS LISTED FOR FLEXIBLE CABLE NEC 400 & 110.3 |
|
| 06/13/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 05/21/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 05/07/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 05/03/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OK PANELS EAST & WEST ENDS OF MAIN EQUIPMENT ROOM 2. OK 112.5 KVA & 75 KVA TRANSFORMERS IN MAIN SW GEAR ROOMS A & B 3. OK 4 225 KVA TRANSFORMERS 4. OK PANELS UPB, UPA, DPTB1, DPTB2, DPTA1, DPTA2 |
|
| 04/26/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OK MECH A, MECH B, DPA, DPB, LPA, LPB, PPA, PPB 2. OK MIDDLE ROW OF PANELS IN MECH. EQUIPMENT ROOM 3. BONDING JUMPER FROM TRANSFORMERS TO FIRST DISCONNECT ON SECONDARY TO BE SIZED PER NEC 250.30 A5 500 MCM TO BE 1/6 250 MCM TO BE #2 |
|
| 04/23/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/19/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* CHECKED LOCK OUT OF MAIN SERVICE DISCONNECT LOCK OUT ON BUTTON ALSO |
|
| 04/17/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) OK GFI TEST REPAORT MAIN SWITCH GEAR A & B 2) COMPLETE ITEMS FROM INSPECTION ON 4/13/07 3) INSTALL LOCK OUT AS DISCUSSED ON 4/13/07. POWER UP TO MAIN BREAKER ONLY. MAIN BREAKER TO BE LOCKED OUT |
|
| 04/13/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OK CEILINGS RMS 101, 102, 103 & 121 2. NEED TO BOND WATER, STEEL & SPRINKLER TO SERVICES 3. PROVIDE LETTER OF TORQUE 4. RECALL FOR FEEDERS TO PANELS, ETC 5. NEED INSTRUCTION MANUAL FOR SWITCH GEAR 6. NEED PERFORMANCE TEST OF SWITCHGEAR GFCI 7. OK GROUND RING AROUND BUILDING. |
|
| 04/11/2007 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/19/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. MAIN EQUIPMENT ROOM 119 UNDER FLOOR FROM CENTER PANELS TO GUTTERS. 2. WALLS IN FOLLOWING ROOMS 118, MAIN SERVICE A MAIN SERVICE B OK |
|
| 03/15/2007 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* NO ONE ON SITE TO DIRECT TO INSPECTION AREA |
|
| 03/06/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | FOLLOWING ROOMS OK TO COVER 102, 103, 104, 105, 106, 107, 108, 110, 111, 112, 113, 114, 115 |
|
| 02/26/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* OK WALLS TEC CO ROOM & OUTSIDE PERIMETER WEST & NORTH |
|
| 02/22/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* LOADING DOCK RM 122, MAIN EQM'T ROOM 119 OK TO COVER |