Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date |
Description |
Inspector |
Results |
Comments |
| 02/09/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
|
| 12/02/2009 |
ENGINEERING PRE-CONSTRUCTION |
|
Continued |
SPOKE WITH LOREN MAKUS REGARDING STATUS OF AS-BUILTS. APPROVAL WAS GIVEN 12/2/09. CALLED CONTRACTOR AND INFORMED HIM THAT AS-BUILTS HAD BEEN APPROVED. HE WILL CALL IN FOR FINAL INSPECTION EARLY NEXT WEEK.--NEED TO CHECK THAT COLLAR HAS BEEN PLACED ON BUBBLER AND THAT H/C SIGNAGE HEIGHT IS CORRECT. |
| 04/27/2007 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |