Permit: T06BU01916

Parcel: 141011120


Addresses:

10901 E DREXEL RD

Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Date Description Inspector Results Comments
06/03/2008 ENGINEERING PRE-CONSTRUCTION Approved STORMWATER PRE-CON DOCUMENT HAS BEEN COMPLETED BY KARL RYAN WITH THE EXCEPTION OF ITEMS COVERED IN THE D.O.T. PRE-CON DOCUMENT.
02/12/2008 ENGINEERING PRE-CONSTRUCTION Partial Approval I MET WITH KARL RYAN TO REVIEW THE PRE-CON FORM, KARL WILL REVIEW THE FORM AND HE WILL COPY AND SIGN AT A LATER DATE.
01/28/2008 ENGINEERING PRE-CONSTRUCTION Partial Approval PARTIAL APPROVAL
MEET WITH KARL RYAN/PULTE HOMES AND MIKE BAUER/BORDERLAND.
DUE TO THE SIZE OF THIS PROJECT, THE GRUBBING OF THE SITE WILL BE COMPLETED IN PHASES, THE GRADING CONTRACTOR WILL INSTALL GRADER TRENCHES AND BERMS TO CONTROL STORMWATER RUN-OFF. INSPECTOR WILL CONDUCT PERIODIC INSPECTIONS DURING THE GRUBBING OPERATIONS TO MONITOR COMPLIANCE WITH SWPPP REQUIREMENTS. A PRE-CONSTRUCTION FORM WILL BE PROVIDED NEXT WEEK.
OK TO GRUB AND BEGIN TRENCH/BERM SWPPP INSTALLATION.