Case: T05FR00531

Parcel: 12418187B


Addresses:

1401 E 20TH ST

Inspection Status: Continued

Inspection History: INSP - REINSPECTION

Date Description Inspector Results Comments
08/21/2007 INSP - REINSPECTION Continued met with Steve to discuss progress of changes. Introduced MA85 as the contact person.
07/03/2007 INSP - REINSPECTION Continued Met with Steve and he will contact contractor and have him give us an approx. date for completion.
06/27/2007 INSP - REINSPECTION Continued Spoke with Gal Witmer (architect) and she informed me of the talks with DSD building inspectors, particularly Steve Long. They have hired a licensed contractor (Daniel Montano) to do the work. Follow up with owners for an estimated time of completion.
05/10/2007 INSP - REINSPECTION Continued Plans approved by DSD on 1/04/07. Permits issued on 4/21/07 and expire on 10/21/07. Work to begin soon.
07/26/2006 INSP - REINSPECTION Continued Spoke with Leonard about no contact from architect. He will contact her and advise. Plans have been submitted to COT.
03/22/2006 INSP - REINSPECTION Continued Plans are complete and contact with architect was made. Gayle Witmer will fax a time line of when the actual construction will begin. Owner's plans show the addition of fire doors in lieu of sprinklers.