Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/30/2007 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* TWO 2" RPPBP'S INSTALLED AND CONNECTED TO METER AND BUILDING SUPPLY LINES. |
|
| 03/23/2007 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* HAVE PLUMBER CAULK OR OTHERWISE SEAL GAP BETWEEN PIPE AND FLANGE OK TO SET W.C |
|
| 03/20/2007 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1. PROVIDE CITY APPROVED PLAN OF REDLINS WITH BOTH ON SITE. 2. INSTALL LAV CARRIERS OR HAVE THEM REMOVED FROM PLUMBING SCHEDULE. 3. SECURE MECHANICAL CLOSET FLANGES TO FLOOR. |
|
| 02/15/2007 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* PROVIDE REDLINE DRAWING FOR ALL CHANGES TO POTABLE AND INDUSTRIAL WATER SUPPLY WHICH WILL REQUIRE REDLINE & CITY APPROVED PLAN TO BE ON SITE AT LATER DATE. ALL PIPING WILL REQUIRE LABELING ON IT IDENTIFYING WHICH TYPE OF WATER IT IS. |
|
| 01/12/2007 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* PER REDLINE ON SITE (2) 2" YARD WATER (PVC) FROM METER LOCATION TO COPPER STUB UPS AT NORTHWEST CORNER OF BUILDING WATER TEST OK 1. SHALL SEE BACKFLOW INSTALL, CONNECTION TO BUILDING & METER. INTERCEPTOR OK SHALL PROVIDE REVISED APPROVED PLAN AT FUTURE. |
|
| 01/11/2007 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. WATER TEST WASTE & VENT THRU ROOF NORTHEAST RESTROOMS 113, 114 INCLUDING EDF-1 OK 2. WATER PIPING IN WALL & OVERHEAD FROM WATER HEATER THRU RESTROOMS & EDR BACK TO 1" CW SUPPLY OVERHEAD STUB OUT OF SOUTH WALL OF RESTROOM AREA OK 3. OK TO MAKE CROSSINGFOR (2) 2" YARD WATERS REDLINE ON SITE. |
|
| 01/10/2007 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* SOUTH RESTROOMS & BREAKROOM WATER TEST WASTE & VENT THRU ROOF, WATER PIPING AIR TEST FROM 1" AT WATER HEATER THRU RESTROOM & BREAKROOM OK (ONLY) |
|
| 01/08/2007 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1. SEWER CONNECTION OK 2. REQUIRE TEST ON DWV |
|
| 12/19/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* |