Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/31/2006 | ENGINEERING - FINAL | Approved | ||
| 01/26/2006 | ENGINEERING - FINAL | Partial Approval | TEMP C OF O FOR ENGINEERING APPROVED. PERMANENT C OF O NOT TO BE GIVEN UNTIL ALL ASSOCIATED SITE WORK IS COMPLETED TO INCLUDE: 1) ADDRESS PAVING ISSUE W/ NORTH SIDE OF PROPERTY. 2) ENSURE ALL LANDSCAPING IS DONE PER PLAN. 3) PATCH ASPHALT IN SE CORNER OF PROPERTY. 4) INSTALL AN UNOBSTRUCTED PEDESTRIAN CIRRCULATION PATHWAY FROM THE BLDG. TO THE RIGHT OF WAY. NOTE: BLDG MUST NOT BE OCCUPIED PRIOR TO RECEIVING A CERTIFICATE OF OCCUPANCY. |
|
| 01/04/2006 | ENGINEERING - FINAL | Denied | PRIOR TO THE ISSUANCE OF A COF O FOR ENGINEERING, PROVIDE THE FOLLOWING: 1) COMPLETE ALL DRAINAGE WORK PER YOUR APPROVED SITE AND/OR GRADING PLAN. 2) PROVIDE A SAFE ENVIRONMENT FOR OCCUPANTS. SEPARATE CONSTRUCTION ACTIVITY FROM PUBLIC/EMPLOYEES. 3) ANY SIGNIFICANT CHANGES TO THE APPROVED SET OF PLANS MUST BE RE-APPROVED BY THE ENGINEER OF RECORD AND THE CITY OF TUCSON. 4) PROVIDE AN UNOBSTRUCTED PEDESTRIAN CIRRCULATION PATH FROM THE BLDG TO THE RIGHT OF WAY. 5) PROVIDE PARKING PER YOUR PLAN FOR OCCUPANTS OF BLDG. 6) PROVIDE ACCESS TO TRASH DUMPSTER. 7) ENSURE THERE ARE NO OUTSTANDING OR POTENTIAL LIFE/SAFETY HAZARDS ON SITE. |
|
| 12/22/2005 | ENGINEERING - FINAL | Not ready for Inspection |