Permit: T05CM01056

Parcel: 114540630

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
03/17/2006 ENGINEERING - FINAL Approved
03/13/2006 ENGINEERING - FINAL Denied 1. COMPLETE STRIPING ON NW AND NE CORNERS OF SITE.
2. PROVIDE A DEFINED DRAINAGE SWALE TO CONVEY STORMWATER FROM THE EAST SIDE OF THE BUILDING TO THE R/D BASIN.
3. REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS.
03/09/2006 ENGINEERING - FINAL Denied NOT READY SEE PREVIOUS COMMENTS
02/27/2006 ENGINEERING - FINAL Denied 1. COMPLETE SIDEWALK AND R/D BASIN WEIR OUTLET AT THE SOUTHWEST CORNER OF THE SITE.
2. PROVIDE BICYCLE PARKING.
3. COMPLETE HANDICAP RAMP AND STRIPING AT NW CORNER OF SITE.
4. PROVIDE A CERTIFIED LETTER FROM THE ENGINEER THAT STATES THAT THE R/D BASIN IS CONSTRUCTED IN SUBSTANTIAL CONFORMANCE WITH THE PLAN AND WILL FUNCTION AS DESIGNED.