Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2007 | ENGINEERING - FINAL | Approved | Contractor completed punch list. | |
| 06/11/2007 | ENGINEERING - FINAL | Denied | Contractor needs to: 1- Close out grading permit. 2- Provide letter from engineer in regards to drainage per chapter XIV, section 14.2(7). 3- Repair asphalt in parking area. (old ramp) 4- Remove all wash out from existing basin. 5- repair asphalt next to loading dock. 6- Repair existing basin. Disturbed by sewer line construction. 7- Clean construction material from basin inlet. 8- Complete westside inlet to existing basin. Spoke to Fred site super in regards to issues. |