Permit: T05BU01300

Parcel: 136087950


Addresses:

9510 E 22ND ST


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T05BU01300

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
04/20/2007 GRADING - INTERMEDIATE Approved
02/01/2007 GRADING - INTERMEDIATE Partial Approval MET WITH JASON REGARDING BOLLARDS IN TRASH ENCLOSURE
01/25/2007 GRADING - INTERMEDIATE Correction Required JERRY AND JASON ON SITE
REMINDED THEM OF THE NEED FOR A BASIN CERTIFICATION LETTER
SEE PICS 1987-1990 FOR CONCERNS IN SE CORNER OF SITE WHERE EXISTING ARROYO IS DIRECTED INTO A NEW DRAINAGE WAY
01/23/2007 GRADING - INTERMEDIATE Correction Required WALKED ENTIRE SITE WITH JASON CAGLE W/ TL ROOF
REVIEWED DEFICIENCIES (PARTIAL PUNCHLIST)

-NEW SIDEWALK AT NE CORNER IS AT 3%, 5% IS MAX
-REVISIONS NEED TO BE TURNED IN FOR CHANGES TO WALKWAY INCLUDING PLANTER AREA, RETAINING STRUCTURES AND GENERAL PATH CHANGE
-EAST INLET TO DRAINAGEWAY NEEDS TO BE ADDRESSED. FINAL FINISH WORK IS NOT CALLED OUT ON PLANS
-POSITIVE DRAINAGE MUST BE ESTABLISHED IN ALL BASINS
01/10/2007 GRADING - INTERMEDIATE Correction Required MET ON SITE WITH JASON
WENT THROUGH PLANS AND WALKED SITE
01/03/2007 GRADING - INTERMEDIATE Correction Required MET WITH JASON ON SITE
RICK ENGINEERING TO RESUBMIT CHANGES TO COT FOR REVIEW-NOT SURE WHEN
CLEAN UP WORK ON SITE CONTINUES
12/13/2006 GRADING - INTERMEDIATE Correction Required PICS 1804-1806
CHANGES TO RAMP NOT ON MY SET OF PLANS
EMAIL TO LAITH FOR GUIDANCE
11/14/2006 GRADING - INTERMEDIATE Partial Approval SITE WORK CONTINUES
PAVING BEHIND VILLAGE INN STILL NOT COMPLETE
RAILING BEING INSTALLED AROUND DRAINAGEWAY
10/04/2006 GRADING - INTERMEDIATE Partial Approval WALKED SITE WITH JIM CASEBOLT

PAVING WORK CONTINUES
DISCUSSED SEPARATING CONSTRUCTION TRAFFIC AND GENERAL PUBLIC ACCESS
08/01/2006 GRADING - INTERMEDIATE Partial Approval MET ON SITE WITH TL ROOF/OWNER COORDINATOR/BUILDING INSPECTOR
ALL SITE WORK MUST BE COMPLETE FOR PERM C OF O-ANY INCOMPLETE SITE WORK MUST BE CONSTRUCTION FENCED OFF
ALL PAVING, STRIPING, DRAINAGE, ADA ACCESS, LIFE/SAFETY ISSUES MUST BE COMPLETE
06/13/2006 GRADING - INTERMEDIATE Partial Approval DRAINAGE PIPES BEING INSTALLED BY DAR HIL
SOME CLEAN UP AT TRENCH SITE (S OF AM PM) NEEDED