Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T05BU01300

Parcel: 136087950


Addresses:

9510 E 22ND ST


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T05BU01300

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
06/28/2007 STORMWATER FOLLOW-UP INSP Approved
06/12/2007 STORMWATER FOLLOW-UP INSP Correction Required STANDING WATER AFTER SMALL RAIN EVENT 6/11 SEE PICS
04/20/2007 STORMWATER FOLLOW-UP INSP Approved
08/14/2006 STORMWATER FOLLOW-UP INSP Partial Approval SITE IS PARTIALLY PAVED
CURBING BEING INSTALLED ALONG OLD SPAN TRL
07/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval SITE BEING MAINTAINED-NO TRACK OUT
07/25/2006 STORMWATER FOLLOW-UP INSP Partial Approval TALKED TO JASON CAGLE ON SITE

MEET SET FOR 8/1 AT 11 ON SITE FOR PRE C OF O
07/12/2006 STORMWATER FOLLOW-UP INSP Partial Approval MET WITH JIM CASEBOLT
NO STORMWATER CONCERNS AT THIS TIME
DISCUSSED TEMP C OF O PROCEEDURE AND WHAT ITEMS I WILL BE LOOKING FOR (EVERYTHING)
06/27/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO STORMWATER CONCERNS AT THIS TIME
CONCRETE FORMS IN PLACE AT SW CORNER WHERE DRAINAGE PIPES ARE PLACED
06/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
05/03/2006 STORMWATER FOLLOW-UP INSP Partial Approval MET WITH JOHN
SITE WORK CONTINUES
NO CONCERNS AT THIS TIME
04/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
04/17/2006 STORMWATER FOLLOW-UP INSP Partial Approval SITE WORK CONTINUES
NO CONCERNS AT THIS TIME
04/11/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
04/05/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
03/27/2006 STORMWATER FOLLOW-UP INSP Partial Approval STOPPED AT SITE AND VISITED WITH JIM CASEBOLT

DRAINAGE IS ALMOST COMPLETELY ROUGH GRADED IN AROUND SOUTH SIDE OF SITE
ADDITIONAL SWPPP WILL BE PLACED AT INLET TO EXISTING DRAINAGE WHEN GRADING IS COMPLETED AT WEST SIDE
TRACK OUT HAS BEEN MANAGED
NO FURTHER CONCERNS FROM THE NEIGHBORHOOD TO THE SOUTH HAVE BEEN FORWARDED TO ME
03/21/2006 STORMWATER FOLLOW-UP INSP Partial Approval TRACK OUT IS BEING SWEPT
NO CONCERNS
03/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO TRACK OUT
SEDIMENT CONTROLS IN PLACE
03/17/2006 STORMWATER FOLLOW-UP INSP Partial Approval SPOKE TO TOM HOFFMAN 207-4596. HE HAD CONCERNS REGARDING THE DRAINAGEWAY FROM THE SUBDIVISION ON THE SOUTH SIDE OF THE PROJECT. HE WAS CONCERNED THAT THE DRAINAGE WAY WOULD BE BLOCKED OFF. THERE IS GOING TO BE A DRAINAGE WAY ALONG THE SOUTH SIDE OF THE MARKETPLACE. SPOKE WITH KEVIN W/ TL ROOF (PROJECT MANAGER) ON SITE TO VERIFY DRAINAGE WAY IS ROUGH GRADED TO PLAN.
03/14/2006 STORMWATER FOLLOW-UP INSP Approved SITE IS BEING MAINTAINED
TRACK OUT IS BEING SWEPT REGULARLY
03/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval SWEEPING TAKING PLACE REGULARLY
TRUCKING IS STILL DEPOSITING A LARGE AMOUNT OF DIRT/TRACKING ON STREET
03/03/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
02/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS AT THIS TIME
DIGGUM AND SONS IS DOING THE SWEEPING FOR THE SITE
SAW THE SWEEPING TODAY.