Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) 2" C.W. SUPPLY @ LEC BLDG AND 1 1/2 C.W. SUPPLY FOR ADMIN BLDG IS OK. AIR PRESSURE TEST IS OK |
|
| 04/21/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1ST PAHSE WRAP ON ABS PRE POUR | |
| 04/14/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* TEST ON P-10 IN ROOM # 132 TEST OK WILL NEED TO WRAP ALL WAST IN SLAB | |
| 03/28/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SOIL WATER TEST IS OK. 2) NOTE: 4" BUILDING DRAIN IS STUBBED OUT OF STRUCTURE 2'-0". 3) OK TO BACKFILL TRENCH. 4) THIS INSPECTION IS FOR BLDG 1 ONLY |