Date Description Inspector Results Comments
05/04/2005 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :* REVISED CITY APPROVED PLAN ON SITE.
01/14/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/WATER TEST WASTE & VENT UNDERGROUND FOR SCIENCE & CHEMISTRY AREA OF BUILDING 3 OK PER HIGHLIGHTED & INITALED PLAN IN TRAILER. THIS PIPING IS ABS DWV PLEASE PROVIDE INFORMATION ABOUT ACID NEUTRALIZATION PIPING FOR WASTE & VENT IN THIS AREA. COVER AT OWN RISK
01/05/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*WASTE & VENT WATER TEST FROM 2-WAY CLEANOUT THRU TO RESTROOM 357, 358, WORKROOM 360, EWE 356, CLASSROOM & CLASSROOM 362 OK PER HIGHLIGTED & INIALED PLAN IN TRAILER
01/03/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 3" H2O SERVICE FOR BUILDING #3 STUB? UP 3' AND OUT 5' SILVER ??UNDER SLAB OK 90PSI TEST
12/30/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :WATER TEST WASTE AND VENT UNDERGROUND ONLY UNISEX 322 +323
AND P-8 IN WORK AREA 317 OK
12/29/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/WATER TEST WASTE & VENT UNDERGROUND ONLY RESTROOM 326 & 327, 314 & 315 INCLUDING EWC AT 333 & 334 AND EWC AT 307 & 308 OK. 1)WILL NEED REVISION FOR VERTICAL DRAINAGE FOR STOOLS SIZING. COVER AT OWN RISK.
11/29/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/4" BUILDING DRAIN FROM BUILDING 2 WAY CLEANOUT STUBBED INTO BUILDING PER INITIALED & HIGHLIGHTED PLAN IN TRAILER. WATER TEST OK.