Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2019 | PLUMBING - GAS PRESS TEST FNL | Approved | OK to clear gas | |
| 12/27/2018 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | gas piping outside has already been approved and tested previously. In order to get gas clearance appliances need to be installed, water heater needs to be installed, current water heater location is not per drawing | |
| 07/02/2018 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* TEST OK NEW LINE PER REVISION FROM METER TO HOUSE ONLY |
|
| 01/08/2018 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | LEFT MSSGS | |
| 02/10/2017 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | SUBMIT AS BUILT FOR NEW GAS LINE LOCATED SOUTH OF HOUSE TO RELOCATE METER NOT ON PLAN OR OBTAIN SEPERATE PERMIT. |