Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T04CM00284
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/29/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
02/25/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) NOT READY FOR INSPECTION | |
02/15/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* DELI BAKERY WALLS ONLY WASTE, VENTS & WATER. PHOTO CENTER WALLS ONLY WASTE, VENTS, & WATER. PRODUCE, DAIRY, BREAK ROOM, MEAT COOLER AREAS WALLS ONLY. WAST, VENTS & WATER IN WALLS ONLY. OK PLEASE PROVIDE INSULATION & NAIL PROTECTION AS REQUIRED. SEE P-3 | |
01/14/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/2ND POOL WRAO IJ | |
01/10/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SEE NEW REVISION OF 1/5/05 SEC. P-1 2) WATER TEST OK AT THIS TIME |
|
12/27/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :*/PLEASE PROVIDE A SET OF APPROVED REVISED PLANS BEFORE NEXT INSP. REVISION ON UNDERGROUND AT THIS TIME NOT READY | |
12/01/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/UNDERGROUND WASTE INSIDE BLDG 4TH PHASE. SEE P-1 | |
11/26/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :4" GREASE WASTE FROM INITALED ON APPROVED PLAN WATER TEST 3" COMBINATION WASTE & VENT INCLUDING (3) 3" FLOOR SINKS + (4) 4" FLOOR SINKS INITALED ON PLAN WATER TEST OK |
|
11/22/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/TEST OK ON 3RD PHASE SEC P-1 | |
11/18/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/TEST OK SEC PLAN-P-1 FOR UNDERGROUND | |
11/16/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/2ND PHASE EAST SIDE SEE PLAN P-1. TEST OK. OK TO BACKFILL. | |
11/09/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/TEST ON 1ST PHASE COMBINATION WASTE AND VENT. TEST OK ON UNDERGROUND WASTE. SEE APPROVED PLAN P-1 |